Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 64 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.Which of these is poor project planning? (a) forgetting the due date (b) checking progress weekly (c) using a simple timetable (d) keeping spare days
  2. 2.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
  3. 3.Which of these is poor project planning? (a) breaking work into steps (b) using a simple timetable (c) no task list (d) starting early
  4. 4.Which of these is poor project planning? (a) no spare time (b) using a simple timetable (c) keeping spare days (d) setting mini-deadlines
  5. 5.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) there is no need (c) for surprises (d) to rest only
  6. 6.Which of these is good project planning? (a) starting on the last day (b) ignoring the timetable (c) forgetting the due date (d) keeping spare days
  7. 7.True or false: “starting early” is poor project planning. (a) False (b) True
  8. 8.⏰ You start at 4:45 PM. Homework takes 25 minutes, then project work takes 40 minutes. When will you finish? (a) 6:05 PM (b) 5:10 PM (c) 5:25 PM (d) 5:50 PM
  9. 9.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) play first (c) make the poster (d) study for the test
  10. 10.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
  11. 11.True or false: “setting mini-deadlines” is good project planning. (a) True (b) False
  12. 12.🔍 Which is the odd one out? (a) starting early (b) one huge deadline (c) listing tasks first (d) checking progress weekly
  13. 13.Which of these is good project planning? (a) doing only easy bits (b) no spare time (c) no task list (d) setting mini-deadlines
  14. 14.🔍 Which is the odd one out? (a) keeping spare days (b) using a simple timetable (c) hard part first (d) ignoring the timetable
  15. 15.🔍 Which is the odd one out? (a) starting on the last day (b) setting mini-deadlines (c) listing tasks first (d) breaking work into steps
  16. 16.Which of these is poor project planning? (a) using a simple timetable (b) starting early (c) one huge deadline (d) breaking work into steps
  17. 17.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
  18. 18.✂️ Your team must make 15 paper flowers in 5 days, the same number each day. How many paper flowers a day?
  19. 19.⏰ You start at 5:45 PM. Homework takes 45 minutes, then project work takes 15 minutes. When will you finish? (a) 7:00 PM (b) 6:30 PM (c) 6:45 PM (d) 6:00 PM
  20. 20.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) this week (d) the night before
  21. 21.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
  22. 22.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
  23. 23.📅 Your school play is due in 9 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  24. 24.True or false: “keeping spare days” is good project planning. (a) False (b) True
  25. 25.🔍 Which is the odd one out? (a) guessing how long (b) keeping spare days (c) no task list (d) doing only easy bits
  26. 26.Which of these is poor project planning? (a) using a simple timetable (b) setting mini-deadlines (c) guessing how long (d) starting early
  27. 27.📅 Your school play is due in 11 days. Research takes 1 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  28. 28.🔍 Which is the odd one out? (a) guessing how long (b) hard part first (c) setting mini-deadlines (d) listing tasks first
  29. 29.Which of these is good project planning? (a) ignoring the timetable (b) starting early (c) forgetting the due date (d) one huge deadline
  30. 30.True or false: “hard part first” is poor project planning. (a) False (b) True
  31. 31.📅 Your class magazine is due in 11 days. Research takes 1 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
  32. 32.📅 Your eco-club poster is due in 11 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  33. 33.⏰ You start at 4:45 PM. Homework takes 45 minutes, then project work takes 35 minutes. When will you finish? (a) 6:20 PM (b) 5:20 PM (c) 5:30 PM (d) 6:05 PM
  34. 34.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) wait for help (c) give up (d) break it into steps
  35. 35.🔍 Which is the odd one out? (a) using a simple timetable (b) starting early (c) breaking work into steps (d) forgetting the due date
  36. 36.True or false: “starting on the last day” is good project planning. (a) True (b) False
  37. 37.📅 Your science model is due in 15 days. Research takes 4 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  38. 38.✅ What is a mini-deadline? (a) a date for one step (b) a holiday (c) a late fine (d) the final due date
  39. 39.True or false: “guessing how long” is poor project planning. (a) False (b) True
  40. 40.True or false: “breaking work into steps” is poor project planning. (a) True (b) False

Answer key

  1. forgetting the due date
  2. poor planning
  3. no task list
  4. no spare time
  5. for surprises
  6. keeping spare days
  7. False
  8. 5:50 PM
  9. study for the test
  10. poor planning
  11. True
  12. one huge deadline
  13. setting mini-deadlines
  14. ignoring the timetable
  15. starting on the last day
  16. one huge deadline
  17. good planning
  18. 3
  19. 6:45 PM
  20. this week
  21. False
  22. poor planning
  23. 2
  24. True
  25. keeping spare days
  26. guessing how long
  27. 2
  28. guessing how long
  29. starting early
  30. False
  31. 3
  32. 4
  33. 6:05 PM
  34. break it into steps
  35. forgetting the due date
  36. False
  37. 3
  38. a date for one step
  39. True
  40. False