Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.Which of these is good project planning? (a) using a simple timetable (b) ignoring the timetable (c) doing only easy bits (d) guessing how long
- 2.📅 Your maths exhibit is due in 13 days. Research takes 2 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
- 3.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 4.🔍 Which is the odd one out? (a) keeping spare days (b) one huge deadline (c) forgetting the due date (d) doing only easy bits
- 5.True or false: “starting early” is good project planning. (a) False (b) True
- 6.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) for surprises (c) to start late (d) there is no need
- 7.⏰ You start at 5:45 PM. Homework takes 25 minutes, then project work takes 25 minutes. When will you finish? (a) 6:10 PM (b) 6:50 PM (c) 6:35 PM
- 8.Which of these is good project planning? (a) one huge deadline (b) no task list (c) hard part first (d) ignoring the timetable
- 9.⏰ You start at 4:30 PM. Homework takes 40 minutes, then project work takes 15 minutes. When will you finish? (a) 4:45 PM (b) 5:10 PM (c) 5:25 PM (d) 5:40 PM
- 10.🔍 Which is the odd one out? (a) hard part first (b) forgetting the due date (c) starting early (d) breaking work into steps
- 11.⏰ You start at 5:15 PM. Homework takes 25 minutes, then project work takes 35 minutes. When will you finish? (a) 6:30 PM (b) 5:40 PM (c) 6:15 PM (d) 5:50 PM
- 12.True or false: “one huge deadline” is poor project planning. (a) False (b) True
- 13.🔍 Which is the odd one out? (a) starting on the last day (b) guessing how long (c) one huge deadline (d) starting early
- 14.True or false: “hard part first” is good project planning. (a) True (b) False
- 15.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
- 16.Which of these is good project planning? (a) guessing how long (b) starting on the last day (c) setting mini-deadlines (d) one huge deadline
- 17.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 18.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) neither (c) make the poster (d) play first
- 19.🔍 Which is the odd one out? (a) starting on the last day (b) using a simple timetable (c) breaking work into steps (d) listing tasks first
- 20.True or false: “checking progress weekly” is good project planning. (a) False (b) True
- 21.🔍 Which is the odd one out? (a) breaking work into steps (b) no task list (c) forgetting the due date (d) guessing how long
- 22.✅ What is a mini-deadline? (a) a late fine (b) a holiday (c) a date for one step (d) the final due date
- 23.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
- 24.⏰ You start at 4:45 PM. Homework takes 35 minutes, then project work takes 35 minutes. When will you finish? (a) 5:20 PM (b) 5:55 PM (c) 6:10 PM
- 25.Which of these is good project planning? (a) guessing how long (b) starting on the last day (c) ignoring the timetable (d) breaking work into steps
- 26.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 27.🔍 Which is the odd one out? (a) checking progress weekly (b) no task list (c) one huge deadline (d) starting on the last day
- 28.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
- 29.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) break it into steps (d) do it all at once
- 30.True or false: “hard part first” is poor project planning. (a) True (b) False
- 31.🔍 Which is the odd one out? (a) guessing how long (b) starting early (c) keeping spare days (d) listing tasks first
- 32.True or false: “breaking work into steps” is good project planning. (a) True (b) False
- 33.🔍 Which is the odd one out? (a) no spare time (b) no task list (c) ignoring the timetable (d) listing tasks first
- 34.Which of these is poor project planning? (a) no task list (b) starting early (c) listing tasks first (d) keeping spare days
- 35.🔍 Which is the odd one out? (a) setting mini-deadlines (b) listing tasks first (c) using a simple timetable (d) no spare time
- 36.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) after it is due (c) this week (d) the night before
- 37.✂️ Your team must make 6 thank-you cards in 3 days, the same number each day. How many thank-you cards a day?
- 38.Which of these is poor project planning? (a) forgetting the due date (b) hard part first (c) listing tasks first (d) keeping spare days
- 39.📅 Your school play is due in 8 days. Research takes 2 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 40.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
Answer key
- using a simple timetable
- 4
- good planning
- keeping spare days
- True
- for surprises
- 6:35 PM
- hard part first
- 5:25 PM
- forgetting the due date
- 6:15 PM
- True
- starting early
- True
- poor planning
- setting mini-deadlines
- good planning
- study for the test
- starting on the last day
- True
- breaking work into steps
- a date for one step
- poor planning
- 5:55 PM
- breaking work into steps
- poor planning
- checking progress weekly
- good planning
- break it into steps
- False
- guessing how long
- True
- listing tasks first
- no task list
- no spare time
- this week
- 2
- forgetting the due date
- 1
- poor planning