Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 695 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Your school play is due in 10 days. Research takes 2 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
  2. 2.⏰ You start at 5:45 PM. Homework takes 40 minutes, then project work takes 40 minutes. When will you finish? (a) 7:05 PM (b) 7:20 PM (c) 6:25 PM
  3. 3.Which of these is good project planning? (a) forgetting the due date (b) no task list (c) one huge deadline (d) listing tasks first
  4. 4.True or false: “listing tasks first” is poor project planning. (a) True (b) False
  5. 5.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) give up (c) wait for help (d) break it into steps
  6. 6.⏰ You start at 5:15 PM. Homework takes 35 minutes, then project work takes 15 minutes. When will you finish? (a) 5:30 PM (b) 5:50 PM (c) 6:05 PM (d) 6:20 PM
  7. 7.Which of these is poor project planning? (a) breaking work into steps (b) one huge deadline (c) starting early (d) keeping spare days
  8. 8.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
  9. 9.🔍 Which is the odd one out? (a) no spare time (b) hard part first (c) breaking work into steps (d) setting mini-deadlines
  10. 10.🔍 Which is the odd one out? (a) starting on the last day (b) breaking work into steps (c) checking progress weekly (d) using a simple timetable
  11. 11.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) neither (c) play first (d) make the poster
  12. 12.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
  13. 13.Which of these is good project planning? (a) no task list (b) doing only easy bits (c) guessing how long (d) checking progress weekly
  14. 14.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
  15. 15.Which of these is poor project planning? (a) setting mini-deadlines (b) hard part first (c) keeping spare days (d) ignoring the timetable
  16. 16.🔍 Which is the odd one out? (a) no spare time (b) starting on the last day (c) hard part first (d) no task list
  17. 17.🔍 Which is the odd one out? (a) checking progress weekly (b) hard part first (c) listing tasks first (d) ignoring the timetable
  18. 18.True or false: “forgetting the due date” is good project planning. (a) True (b) False
  19. 19.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
  20. 20.Which of these is good project planning? (a) one huge deadline (b) starting early (c) starting on the last day (d) forgetting the due date
  21. 21.🔍 Which is the odd one out? (a) no spare time (b) guessing how long (c) listing tasks first (d) no task list
  22. 22.🔍 Which is the odd one out? (a) no task list (b) no spare time (c) forgetting the due date (d) keeping spare days
  23. 23.Which of these is good project planning? (a) no task list (b) starting on the last day (c) guessing how long (d) using a simple timetable
  24. 24.✂️ Your team must make 36 paper flowers in 4 days, the same number each day. How many paper flowers a day?
  25. 25.⏰ You start at 3:45 PM. Homework takes 30 minutes, then project work takes 15 minutes. When will you finish? (a) 4:15 PM (b) 4:30 PM (c) 4:00 PM (d) 4:45 PM
  26. 26.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
  27. 27.📅 Your class magazine is due in 10 days. Research takes 2 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  28. 28.🔍 Which is the odd one out? (a) no task list (b) guessing how long (c) forgetting the due date (d) setting mini-deadlines
  29. 29.🔍 Which is the odd one out? (a) checking progress weekly (b) keeping spare days (c) breaking work into steps (d) one huge deadline
  30. 30.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) to rest only (d) for surprises
  31. 31.True or false: “setting mini-deadlines” is poor project planning. (a) False (b) True
  32. 32.✂️ Your team must make 42 bookmarks in 6 days, the same number each day. How many bookmarks a day?
  33. 33.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  34. 34.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
  35. 35.📅 Your maths exhibit is due in 13 days. Research takes 2 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  36. 36.✂️ Your team must make 45 paper bags in 5 days, the same number each day. How many paper bags a day?
  37. 37.Which of these is good project planning? (a) no task list (b) doing only easy bits (c) hard part first (d) forgetting the due date
  38. 38.Which of these is poor project planning? (a) keeping spare days (b) checking progress weekly (c) no task list (d) hard part first
  39. 39.Which of these is good project planning? (a) keeping spare days (b) no task list (c) no spare time (d) guessing how long
  40. 40.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) this week (c) the night before (d) after it is due

Answer key

  1. 2
  2. 7:05 PM
  3. listing tasks first
  4. False
  5. break it into steps
  6. 6:05 PM
  7. one huge deadline
  8. poor planning
  9. no spare time
  10. starting on the last day
  11. study for the test
  12. poor planning
  13. checking progress weekly
  14. False
  15. ignoring the timetable
  16. hard part first
  17. ignoring the timetable
  18. False
  19. poor planning
  20. starting early
  21. listing tasks first
  22. keeping spare days
  23. using a simple timetable
  24. 9
  25. 4:30 PM
  26. good planning
  27. 1
  28. setting mini-deadlines
  29. one huge deadline
  30. for surprises
  31. False
  32. 7
  33. good planning
  34. good planning
  35. 4
  36. 9
  37. hard part first
  38. no task list
  39. keeping spare days
  40. this week