Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 731 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.Which of these is poor project planning? (a) listing tasks first (b) keeping spare days (c) no task list (d) breaking work into steps
  2. 2.📅 Your science model is due in 15 days. Research takes 4 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  3. 3.Which of these is poor project planning? (a) checking progress weekly (b) one huge deadline (c) listing tasks first (d) starting early
  4. 4.✂️ Your team must make 27 bookmarks in 3 days, the same number each day. How many bookmarks a day?
  5. 5.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
  6. 6.Which of these is poor project planning? (a) starting early (b) checking progress weekly (c) setting mini-deadlines (d) no spare time
  7. 7.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
  8. 8.True or false: “no spare time” is poor project planning. (a) True (b) False
  9. 9.⏰ You start at 5:30 PM. Homework takes 25 minutes, then project work takes 30 minutes. When will you finish? (a) 6:00 PM (b) 6:25 PM (c) 6:40 PM (d) 5:55 PM
  10. 10.✂️ Your team must make 20 name badges in 4 days, the same number each day. How many name badges a day?
  11. 11.🧩 A big project feels scary. What should you do first? (a) wait for help (b) break it into steps (c) do it all at once (d) give up
  12. 12.⏰ You start at 3:00 PM. Homework takes 45 minutes, then project work takes 15 minutes. When will you finish? (a) 4:15 PM (b) 3:15 PM (c) 4:00 PM (d) 3:45 PM
  13. 13.🔍 Which is the odd one out? (a) no task list (b) forgetting the due date (c) setting mini-deadlines (d) one huge deadline
  14. 14.True or false: “keeping spare days” is poor project planning. (a) True (b) False
  15. 15.🔍 Which is the odd one out? (a) ignoring the timetable (b) starting early (c) checking progress weekly (d) keeping spare days
  16. 16.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) make the poster (b) play first (c) study for the test (d) neither
  17. 17.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
  18. 18.🔍 Which is the odd one out? (a) keeping spare days (b) using a simple timetable (c) starting early (d) guessing how long
  19. 19.Which of these is good project planning? (a) no spare time (b) setting mini-deadlines (c) forgetting the due date (d) ignoring the timetable
  20. 20.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
  21. 21.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
  22. 22.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) for surprises (d) to rest only
  23. 23.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
  24. 24.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
  25. 25.Which of these is poor project planning? (a) hard part first (b) using a simple timetable (c) listing tasks first (d) forgetting the due date
  26. 26.True or false: “breaking work into steps” is good project planning. (a) True (b) False
  27. 27.Which of these is poor project planning? (a) starting early (b) hard part first (c) setting mini-deadlines (d) starting on the last day
  28. 28.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
  29. 29.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
  30. 30.Which of these is good project planning? (a) keeping spare days (b) starting on the last day (c) ignoring the timetable (d) no task list
  31. 31.🔍 Which is the odd one out? (a) using a simple timetable (b) starting on the last day (c) no task list (d) ignoring the timetable
  32. 32.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) this week (c) after it is due (d) the night before
  33. 33.✂️ Your team must make 54 bookmarks in 6 days, the same number each day. How many bookmarks a day?
  34. 34.Which of these is poor project planning? (a) starting early (b) hard part first (c) using a simple timetable (d) ignoring the timetable
  35. 35.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
  36. 36.True or false: “keeping spare days” is good project planning. (a) True (b) False
  37. 37.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
  38. 38.✂️ Your team must make 14 paper bags in 2 days, the same number each day. How many paper bags a day?
  39. 39.True or false: “starting early” is poor project planning. (a) False (b) True
  40. 40.Which of these is good project planning? (a) ignoring the timetable (b) breaking work into steps (c) starting on the last day (d) no task list

Answer key

  1. no task list
  2. 4
  3. one huge deadline
  4. 9
  5. good planning
  6. no spare time
  7. good planning
  8. True
  9. 6:25 PM
  10. 5
  11. break it into steps
  12. 4:00 PM
  13. setting mini-deadlines
  14. False
  15. ignoring the timetable
  16. study for the test
  17. poor planning
  18. guessing how long
  19. setting mini-deadlines
  20. good planning
  21. good planning
  22. for surprises
  23. poor planning
  24. poor planning
  25. forgetting the due date
  26. True
  27. starting on the last day
  28. poor planning
  29. poor planning
  30. keeping spare days
  31. using a simple timetable
  32. this week
  33. 9
  34. ignoring the timetable
  35. poor planning
  36. True
  37. False
  38. 7
  39. False
  40. breaking work into steps