Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 804 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
  2. 2.True or false: “starting early” is poor project planning. (a) True (b) False
  3. 3.True or false: “no spare time” is good project planning. (a) False (b) True
  4. 4.True or false: “starting early” is good project planning. (a) True (b) False
  5. 5.✂️ Your team must make 12 paper flowers in 2 days, the same number each day. How many paper flowers a day?
  6. 6.✅ What is a mini-deadline? (a) a late fine (b) the final due date (c) a holiday (d) a date for one step
  7. 7.⏰ You start at 3:45 PM. Homework takes 35 minutes, then project work takes 20 minutes. When will you finish? (a) 4:55 PM (b) 4:20 PM (c) 4:05 PM (d) 4:40 PM
  8. 8.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
  9. 9.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
  10. 10.Which of these is good project planning? (a) doing only easy bits (b) starting early (c) starting on the last day (d) guessing how long
  11. 11.🔍 Which is the odd one out? (a) keeping spare days (b) guessing how long (c) ignoring the timetable (d) starting on the last day
  12. 12.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
  13. 13.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) after it is due (c) the night before (d) this week
  14. 14.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  15. 15.🔍 Which is the odd one out? (a) no spare time (b) breaking work into steps (c) ignoring the timetable (d) forgetting the due date
  16. 16.✂️ Your team must make 36 posters in 4 days, the same number each day. How many posters a day?
  17. 17.📅 Your history chart is due in 10 days. Research takes 1 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
  18. 18.📅 Your maths exhibit is due in 13 days. Research takes 3 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
  19. 19.Which of these is poor project planning? (a) breaking work into steps (b) using a simple timetable (c) keeping spare days (d) forgetting the due date
  20. 20.True or false: “hard part first” is good project planning. (a) True (b) False
  21. 21.Which of these is poor project planning? (a) using a simple timetable (b) listing tasks first (c) no task list (d) keeping spare days
  22. 22.📅 Your eco-club poster is due in 7 days. Research takes 1 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
  23. 23.Which of these is good project planning? (a) breaking work into steps (b) guessing how long (c) ignoring the timetable (d) no spare time
  24. 24.Which of these is good project planning? (a) using a simple timetable (b) ignoring the timetable (c) doing only easy bits (d) guessing how long
  25. 25.Which of these is poor project planning? (a) breaking work into steps (b) keeping spare days (c) checking progress weekly (d) ignoring the timetable
  26. 26.🔍 Which is the odd one out? (a) starting early (b) no task list (c) keeping spare days (d) listing tasks first
  27. 27.True or false: “no task list” is poor project planning. (a) False (b) True
  28. 28.Which of these is good project planning? (a) no spare time (b) starting on the last day (c) ignoring the timetable (d) keeping spare days
  29. 29.Which of these is good project planning? (a) doing only easy bits (b) one huge deadline (c) guessing how long (d) hard part first
  30. 30.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) wait for help (c) do it all at once (d) give up
  31. 31.✂️ Your team must make 24 bookmarks in 3 days, the same number each day. How many bookmarks a day?
  32. 32.True or false: “one huge deadline” is poor project planning. (a) True (b) False
  33. 33.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) to start late (c) there is no need (d) for surprises
  34. 34.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
  35. 35.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
  36. 36.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
  37. 37.🔍 Which is the odd one out? (a) listing tasks first (b) forgetting the due date (c) breaking work into steps (d) starting early
  38. 38.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
  39. 39.Which of these is good project planning? (a) forgetting the due date (b) ignoring the timetable (c) doing only easy bits (d) checking progress weekly
  40. 40.Which of these is good project planning? (a) setting mini-deadlines (b) starting on the last day (c) forgetting the due date (d) guessing how long

Answer key

  1. poor planning
  2. False
  3. False
  4. True
  5. 6
  6. a date for one step
  7. 4:40 PM
  8. poor planning
  9. good planning
  10. starting early
  11. keeping spare days
  12. good planning
  13. this week
  14. good planning
  15. breaking work into steps
  16. 9
  17. 3
  18. 3
  19. forgetting the due date
  20. True
  21. no task list
  22. 2
  23. breaking work into steps
  24. using a simple timetable
  25. ignoring the timetable
  26. no task list
  27. True
  28. keeping spare days
  29. hard part first
  30. break it into steps
  31. 8
  32. True
  33. for surprises
  34. poor planning
  35. good planning
  36. good planning
  37. forgetting the due date
  38. good planning
  39. checking progress weekly
  40. setting mini-deadlines