Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
- 2.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 3.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 4.📅 Your school play is due in 15 days. Research takes 4 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 5.🔍 Which is the odd one out? (a) breaking work into steps (b) keeping spare days (c) setting mini-deadlines (d) guessing how long
- 6.⏰ You start at 5:30 PM. Homework takes 40 minutes, then project work takes 40 minutes. When will you finish? (a) 7:05 PM (b) 6:50 PM (c) 6:10 PM
- 7.Which of these is good project planning? (a) one huge deadline (b) guessing how long (c) starting on the last day (d) using a simple timetable
- 8.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 9.🔍 Which is the odd one out? (a) guessing how long (b) hard part first (c) one huge deadline (d) no task list
- 10.True or false: “listing tasks first” is good project planning. (a) False (b) True
- 11.Which of these is poor project planning? (a) no task list (b) starting early (c) using a simple timetable (d) listing tasks first
- 12.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
- 13.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) after it is due (d) the night before
- 14.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) study for the test (d) play first
- 15.🔍 Which is the odd one out? (a) hard part first (b) starting early (c) no task list (d) breaking work into steps
- 16.🔍 Which is the odd one out? (a) ignoring the timetable (b) forgetting the due date (c) breaking work into steps (d) guessing how long
- 17.Which of these is good project planning? (a) guessing how long (b) starting on the last day (c) hard part first (d) ignoring the timetable
- 18.✂️ Your team must make 45 posters in 5 days, the same number each day. How many posters a day?
- 19.True or false: “forgetting the due date” is poor project planning. (a) False (b) True
- 20.🔍 Which is the odd one out? (a) setting mini-deadlines (b) one huge deadline (c) no spare time (d) starting on the last day
- 21.True or false: “one huge deadline” is good project planning. (a) True (b) False
- 22.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
- 23.True or false: “guessing how long” is good project planning. (a) False (b) True
- 24.✂️ Your team must make 18 paper flowers in 2 days, the same number each day. How many paper flowers a day?
- 25.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 26.🔍 Which is the odd one out? (a) ignoring the timetable (b) starting early (c) one huge deadline (d) no task list
- 27.📅 Your history chart is due in 12 days. Research takes 2 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 28.Which of these is good project planning? (a) guessing how long (b) listing tasks first (c) no spare time (d) doing only easy bits
- 29.Which of these is good project planning? (a) forgetting the due date (b) one huge deadline (c) breaking work into steps (d) no task list
- 30.True or false: “checking progress weekly” is poor project planning. (a) False (b) True
- 31.🔍 Which is the odd one out? (a) setting mini-deadlines (b) one huge deadline (c) listing tasks first (d) breaking work into steps
- 32.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
- 33.True or false: “no spare time” is good project planning. (a) False (b) True
- 34.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) there is no need (c) for surprises (d) to start late
- 35.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
- 36.🧩 A big project feels scary. What should you do first? (a) wait for help (b) do it all at once (c) give up (d) break it into steps
- 37.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
- 38.Which of these is good project planning? (a) starting on the last day (b) keeping spare days (c) doing only easy bits (d) no task list
- 39.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
- 40.Which of these is good project planning? (a) checking progress weekly (b) one huge deadline (c) starting on the last day (d) ignoring the timetable
Answer key
- poor planning
- good planning
- good planning
- 3
- guessing how long
- 6:50 PM
- using a simple timetable
- poor planning
- hard part first
- True
- no task list
- False
- this week
- study for the test
- no task list
- breaking work into steps
- hard part first
- 9
- True
- setting mini-deadlines
- False
- good planning
- False
- 9
- good planning
- starting early
- 5
- listing tasks first
- breaking work into steps
- False
- one huge deadline
- poor planning
- False
- for surprises
- poor planning
- break it into steps
- poor planning
- keeping spare days
- poor planning
- checking progress weekly