Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 834 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  2. 2.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  3. 3.🔍 Which is the odd one out? (a) forgetting the due date (b) one huge deadline (c) doing only easy bits (d) listing tasks first
  4. 4.True or false: “starting on the last day” is good project planning. (a) False (b) True
  5. 5.True or false: “using a simple timetable” is poor project planning. (a) False (b) True
  6. 6.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
  7. 7.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) the night before (c) in the third week (d) this week
  8. 8.Which of these is poor project planning? (a) guessing how long (b) breaking work into steps (c) checking progress weekly (d) using a simple timetable
  9. 9.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) break it into steps (c) give up (d) wait for help
  10. 10.✅ What is a mini-deadline? (a) a date for one step (b) a late fine (c) a holiday (d) the final due date
  11. 11.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) for surprises (c) to start late (d) there is no need
  12. 12.⏰ You start at 4:00 PM. Homework takes 30 minutes, then project work takes 20 minutes. When will you finish? (a) 4:20 PM (b) 4:50 PM (c) 4:30 PM (d) 5:05 PM
  13. 13.True or false: “listing tasks first” is good project planning. (a) True (b) False
  14. 14.🔍 Which is the odd one out? (a) starting early (b) breaking work into steps (c) using a simple timetable (d) ignoring the timetable
  15. 15.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
  16. 16.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) play first (d) study for the test
  17. 17.⏰ You start at 5:00 PM. Homework takes 25 minutes, then project work takes 20 minutes. When will you finish? (a) 5:25 PM (b) 5:45 PM (c) 5:20 PM (d) 6:00 PM
  18. 18.True or false: “ignoring the timetable” is good project planning. (a) False (b) True
  19. 19.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
  20. 20.🔍 Which is the odd one out? (a) one huge deadline (b) ignoring the timetable (c) starting on the last day (d) using a simple timetable
  21. 21.Which of these is poor project planning? (a) breaking work into steps (b) doing only easy bits (c) starting early (d) hard part first
  22. 22.Which of these is good project planning? (a) one huge deadline (b) starting on the last day (c) doing only easy bits (d) hard part first
  23. 23.Which of these is poor project planning? (a) breaking work into steps (b) forgetting the due date (c) keeping spare days (d) using a simple timetable
  24. 24.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
  25. 25.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  26. 26.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
  27. 27.🔍 Which is the odd one out? (a) starting on the last day (b) checking progress weekly (c) breaking work into steps (d) using a simple timetable
  28. 28.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
  29. 29.🔍 Which is the odd one out? (a) keeping spare days (b) one huge deadline (c) doing only easy bits (d) ignoring the timetable
  30. 30.True or false: “using a simple timetable” is good project planning. (a) False (b) True
  31. 31.🔍 Which is the odd one out? (a) no spare time (b) checking progress weekly (c) listing tasks first (d) setting mini-deadlines
  32. 32.Which of these is good project planning? (a) keeping spare days (b) guessing how long (c) no task list (d) starting on the last day
  33. 33.🔍 Which is the odd one out? (a) guessing how long (b) listing tasks first (c) hard part first (d) breaking work into steps
  34. 34.✂️ Your team must make 16 paper flowers in 2 days, the same number each day. How many paper flowers a day?
  35. 35.True or false: “no spare time” is poor project planning. (a) True (b) False
  36. 36.📅 Your history chart is due in 12 days. Research takes 2 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
  37. 37.Which of these is poor project planning? (a) keeping spare days (b) listing tasks first (c) setting mini-deadlines (d) ignoring the timetable
  38. 38.🔍 Which is the odd one out? (a) starting early (b) listing tasks first (c) using a simple timetable (d) doing only easy bits
  39. 39.📅 Your class magazine is due in 10 days. Research takes 3 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  40. 40.True or false: “breaking work into steps” is good project planning. (a) False (b) True

Answer key

  1. good planning
  2. good planning
  3. listing tasks first
  4. False
  5. False
  6. good planning
  7. this week
  8. guessing how long
  9. break it into steps
  10. a date for one step
  11. for surprises
  12. 4:50 PM
  13. True
  14. ignoring the timetable
  15. poor planning
  16. study for the test
  17. 5:45 PM
  18. False
  19. poor planning
  20. using a simple timetable
  21. doing only easy bits
  22. hard part first
  23. forgetting the due date
  24. good planning
  25. good planning
  26. False
  27. starting on the last day
  28. poor planning
  29. keeping spare days
  30. True
  31. no spare time
  32. keeping spare days
  33. guessing how long
  34. 8
  35. True
  36. 3
  37. ignoring the timetable
  38. doing only easy bits
  39. 2
  40. True