Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 861 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🔍 Which is the odd one out? (a) setting mini-deadlines (b) listing tasks first (c) keeping spare days (d) ignoring the timetable
  2. 2.Which of these is good project planning? (a) using a simple timetable (b) doing only easy bits (c) no spare time (d) starting on the last day
  3. 3.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
  4. 4.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) the night before (c) this week (d) after it is due
  5. 5.True or false: “breaking work into steps” is good project planning. (a) False (b) True
  6. 6.⏰ You start at 5:15 PM. Homework takes 35 minutes, then project work takes 25 minutes. When will you finish? (a) 5:50 PM (b) 6:15 PM (c) 5:40 PM (d) 6:30 PM
  7. 7.Which of these is good project planning? (a) guessing how long (b) keeping spare days (c) no spare time (d) doing only easy bits
  8. 8.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) there is no need (c) for surprises (d) to rest only
  9. 9.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) break it into steps (d) do it all at once
  10. 10.Which of these is poor project planning? (a) listing tasks first (b) keeping spare days (c) breaking work into steps (d) no task list
  11. 11.🔍 Which is the odd one out? (a) starting on the last day (b) no spare time (c) setting mini-deadlines (d) no task list
  12. 12.🔍 Which is the odd one out? (a) breaking work into steps (b) keeping spare days (c) checking progress weekly (d) starting on the last day
  13. 13.✂️ Your team must make 45 bookmarks in 5 days, the same number each day. How many bookmarks a day?
  14. 14.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) play first (d) study for the test
  15. 15.Which of these is poor project planning? (a) setting mini-deadlines (b) using a simple timetable (c) hard part first (d) forgetting the due date
  16. 16.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
  17. 17.🔍 Which is the odd one out? (a) checking progress weekly (b) one huge deadline (c) starting on the last day (d) forgetting the due date
  18. 18.✅ What is a mini-deadline? (a) a late fine (b) a holiday (c) the final due date (d) a date for one step
  19. 19.Which of these is poor project planning? (a) starting on the last day (b) keeping spare days (c) using a simple timetable (d) checking progress weekly
  20. 20.True or false: “starting early” is good project planning. (a) True (b) False
  21. 21.True or false: “setting mini-deadlines” is poor project planning. (a) False (b) True
  22. 22.⏰ You start at 4:30 PM. Homework takes 40 minutes, then project work takes 30 minutes. When will you finish? (a) 5:00 PM (b) 5:40 PM (c) 5:10 PM (d) 5:55 PM
  23. 23.⏰ You start at 4:00 PM. Homework takes 20 minutes, then project work takes 25 minutes. When will you finish? (a) 4:45 PM (b) 4:20 PM (c) 4:25 PM (d) 5:00 PM
  24. 24.⏰ You start at 3:00 PM. Homework takes 30 minutes, then project work takes 30 minutes. When will you finish? (a) 4:00 PM (b) 3:30 PM (c) 4:15 PM
  25. 25.True or false: “hard part first” is good project planning. (a) True (b) False
  26. 26.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
  27. 27.🔍 Which is the odd one out? (a) starting on the last day (b) using a simple timetable (c) guessing how long (d) forgetting the due date
  28. 28.Which of these is good project planning? (a) no spare time (b) checking progress weekly (c) no task list (d) one huge deadline
  29. 29.True or false: “forgetting the due date” is poor project planning. (a) False (b) True
  30. 30.⏰ You start at 4:00 PM. Homework takes 45 minutes, then project work takes 15 minutes. When will you finish? (a) 4:45 PM (b) 4:15 PM (c) 5:15 PM (d) 5:00 PM
  31. 31.True or false: “one huge deadline” is good project planning. (a) True (b) False
  32. 32.True or false: “setting mini-deadlines” is good project planning. (a) True (b) False
  33. 33.True or false: “doing only easy bits” is good project planning. (a) True (b) False
  34. 34.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
  35. 35.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
  36. 36.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
  37. 37.True or false: “checking progress weekly” is poor project planning. (a) False (b) True
  38. 38.Which of these is poor project planning? (a) checking progress weekly (b) no spare time (c) breaking work into steps (d) starting early
  39. 39.📅 Your school play is due in 12 days. Research takes 3 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  40. 40.✂️ Your team must make 12 name badges in 6 days, the same number each day. How many name badges a day?

Answer key

  1. ignoring the timetable
  2. using a simple timetable
  3. poor planning
  4. this week
  5. True
  6. 6:15 PM
  7. keeping spare days
  8. for surprises
  9. break it into steps
  10. no task list
  11. setting mini-deadlines
  12. starting on the last day
  13. 9
  14. study for the test
  15. forgetting the due date
  16. good planning
  17. checking progress weekly
  18. a date for one step
  19. starting on the last day
  20. True
  21. False
  22. 5:40 PM
  23. 4:45 PM
  24. 4:00 PM
  25. True
  26. good planning
  27. using a simple timetable
  28. checking progress weekly
  29. True
  30. 5:00 PM
  31. False
  32. True
  33. False
  34. good planning
  35. False
  36. poor planning
  37. False
  38. no spare time
  39. 1
  40. 2