Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.Which of these is poor project planning? (a) hard part first (b) doing only easy bits (c) starting early (d) setting mini-deadlines
- 2.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) do it all at once (d) break it into steps
- 3.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) play first (c) neither (d) make the poster
- 4.⏰ You start at 5:00 PM. Homework takes 20 minutes, then project work takes 20 minutes. When will you finish? (a) 5:55 PM (b) 5:20 PM (c) 5:40 PM
- 5.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 6.🔍 Which is the odd one out? (a) one huge deadline (b) hard part first (c) checking progress weekly (d) starting early
- 7.Which of these is good project planning? (a) starting on the last day (b) ignoring the timetable (c) keeping spare days (d) no spare time
- 8.Which of these is good project planning? (a) ignoring the timetable (b) guessing how long (c) setting mini-deadlines (d) no spare time
- 9.🔍 Which is the odd one out? (a) ignoring the timetable (b) setting mini-deadlines (c) hard part first (d) breaking work into steps
- 10.🔍 Which is the odd one out? (a) starting on the last day (b) doing only easy bits (c) breaking work into steps (d) ignoring the timetable
- 11.🔍 Which is the odd one out? (a) starting on the last day (b) checking progress weekly (c) ignoring the timetable (d) one huge deadline
- 12.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 13.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
- 14.True or false: “hard part first” is poor project planning. (a) False (b) True
- 15.True or false: “breaking work into steps” is good project planning. (a) False (b) True
- 16.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) after it is due (d) the night before
- 17.✅ What is a mini-deadline? (a) the final due date (b) a date for one step (c) a late fine (d) a holiday
- 18.Which of these is good project planning? (a) doing only easy bits (b) starting on the last day (c) checking progress weekly (d) guessing how long
- 19.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
- 20.True or false: “starting early” is good project planning. (a) True (b) False
- 21.⏰ You start at 3:30 PM. Homework takes 20 minutes, then project work takes 30 minutes. When will you finish? (a) 4:00 PM (b) 4:35 PM (c) 3:50 PM (d) 4:20 PM
- 22.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 23.🔍 Which is the odd one out? (a) starting on the last day (b) keeping spare days (c) forgetting the due date (d) guessing how long
- 24.True or false: “setting mini-deadlines” is good project planning. (a) True (b) False
- 25.True or false: “guessing how long” is good project planning. (a) True (b) False
- 26.🔍 Which is the odd one out? (a) guessing how long (b) no spare time (c) listing tasks first (d) doing only easy bits
- 27.Which of these is good project planning? (a) doing only easy bits (b) forgetting the due date (c) ignoring the timetable (d) listing tasks first
- 28.Which of these is poor project planning? (a) guessing how long (b) checking progress weekly (c) starting early (d) hard part first
- 29.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) for surprises (c) to start late (d) to rest only
- 30.⏰ You start at 3:30 PM. Homework takes 40 minutes, then project work takes 35 minutes. When will you finish? (a) 4:45 PM (b) 4:05 PM (c) 4:10 PM (d) 5:00 PM
- 31.🔍 Which is the odd one out? (a) no spare time (b) starting on the last day (c) starting early (d) doing only easy bits
- 32.🔍 Which is the odd one out? (a) hard part first (b) starting early (c) setting mini-deadlines (d) forgetting the due date
- 33.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
- 34.🔍 Which is the odd one out? (a) doing only easy bits (b) setting mini-deadlines (c) keeping spare days (d) breaking work into steps
- 35.📅 Your eco-club poster is due in 8 days. Research takes 1 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 36.✂️ Your team must make 32 bookmarks in 4 days, the same number each day. How many bookmarks a day?
- 37.True or false: “checking progress weekly” is good project planning. (a) False (b) True
- 38.📅 Your eco-club poster is due in 13 days. Research takes 1 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 39.⏰ You start at 3:00 PM. Homework takes 25 minutes, then project work takes 35 minutes. When will you finish? (a) 3:35 PM (b) 4:00 PM (c) 3:25 PM (d) 4:15 PM
- 40.✂️ Your team must make 10 name badges in 5 days, the same number each day. How many name badges a day?
Answer key
- doing only easy bits
- break it into steps
- study for the test
- 5:40 PM
- poor planning
- one huge deadline
- keeping spare days
- setting mini-deadlines
- ignoring the timetable
- breaking work into steps
- checking progress weekly
- good planning
- True
- False
- True
- this week
- a date for one step
- checking progress weekly
- good planning
- True
- 4:20 PM
- good planning
- keeping spare days
- True
- False
- listing tasks first
- listing tasks first
- guessing how long
- for surprises
- 4:45 PM
- starting early
- forgetting the due date
- poor planning
- doing only easy bits
- 1
- 8
- True
- 4
- 4:00 PM
- 2