Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.Which of these is poor project planning? (a) starting on the last day (b) starting early (c) breaking work into steps (d) checking progress weekly
- 2.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 3.📅 Your art display is due in 9 days. Research takes 1 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 4.Which of these is poor project planning? (a) starting early (b) checking progress weekly (c) guessing how long (d) keeping spare days
- 5.🔍 Which is the odd one out? (a) hard part first (b) checking progress weekly (c) setting mini-deadlines (d) one huge deadline
- 6.True or false: “no task list” is good project planning. (a) True (b) False
- 7.🔍 Which is the odd one out? (a) guessing how long (b) using a simple timetable (c) listing tasks first (d) starting early
- 8.True or false: “forgetting the due date” is good project planning. (a) False (b) True
- 9.🔍 Which is the odd one out? (a) starting on the last day (b) keeping spare days (c) hard part first (d) setting mini-deadlines
- 10.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) study for the test (c) make the poster (d) neither
- 11.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 12.🔍 Which is the odd one out? (a) no task list (b) breaking work into steps (c) one huge deadline (d) forgetting the due date
- 13.True or false: “starting on the last day” is good project planning. (a) True (b) False
- 14.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) for surprises (d) to rest only
- 15.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
- 16.🔍 Which is the odd one out? (a) hard part first (b) no task list (c) starting on the last day (d) one huge deadline
- 17.Which of these is poor project planning? (a) listing tasks first (b) checking progress weekly (c) using a simple timetable (d) ignoring the timetable
- 18.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) wait for help (c) do it all at once (d) give up
- 19.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
- 20.True or false: “starting early” is poor project planning. (a) False (b) True
- 21.True or false: “listing tasks first” is poor project planning. (a) False (b) True
- 22.✂️ Your team must make 8 name badges in 2 days, the same number each day. How many name badges a day?
- 23.🔍 Which is the odd one out? (a) starting early (b) no spare time (c) doing only easy bits (d) ignoring the timetable
- 24.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 25.⏰ You start at 3:15 PM. Homework takes 35 minutes, then project work takes 15 minutes. When will you finish? (a) 4:20 PM (b) 3:30 PM (c) 4:05 PM (d) 3:50 PM
- 26.Which of these is poor project planning? (a) setting mini-deadlines (b) breaking work into steps (c) no task list (d) listing tasks first
- 27.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a date for one step (d) a holiday
- 28.Which of these is poor project planning? (a) breaking work into steps (b) one huge deadline (c) hard part first (d) listing tasks first
- 29.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 30.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) this week (d) the night before
- 31.⏰ You start at 3:00 PM. Homework takes 40 minutes, then project work takes 30 minutes. When will you finish? (a) 3:30 PM (b) 4:25 PM (c) 4:10 PM (d) 3:40 PM
- 32.🔍 Which is the odd one out? (a) no spare time (b) keeping spare days (c) starting early (d) breaking work into steps
- 33.True or false: “one huge deadline” is good project planning. (a) True (b) False
- 34.✂️ Your team must make 48 name badges in 6 days, the same number each day. How many name badges a day?
- 35.True or false: “hard part first” is good project planning. (a) False (b) True
- 36.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
- 37.Which of these is good project planning? (a) ignoring the timetable (b) listing tasks first (c) forgetting the due date (d) no task list
- 38.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
- 39.Which of these is poor project planning? (a) starting early (b) listing tasks first (c) keeping spare days (d) no spare time
- 40.Which of these is good project planning? (a) ignoring the timetable (b) forgetting the due date (c) no spare time (d) setting mini-deadlines
Answer key
- starting on the last day
- poor planning
- 3
- guessing how long
- one huge deadline
- False
- guessing how long
- False
- starting on the last day
- study for the test
- poor planning
- breaking work into steps
- False
- for surprises
- good planning
- hard part first
- ignoring the timetable
- break it into steps
- good planning
- False
- False
- 4
- starting early
- poor planning
- 4:05 PM
- no task list
- a date for one step
- one huge deadline
- poor planning
- this week
- 4:10 PM
- no spare time
- False
- 8
- True
- good planning
- listing tasks first
- True
- no spare time
- setting mini-deadlines