← Managing time on a project lesson New set →

Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 91 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🔍 Which is the odd one out? (a) keeping spare days (b) ignoring the timetable (c) one huge deadline (d) forgetting the due date
  2. 2.🔍 Which is the odd one out? (a) using a simple timetable (b) checking progress weekly (c) hard part first (d) guessing how long
  3. 3.✂️ Your team must make 18 paper flowers in 6 days, the same number each day. How many paper flowers a day?
  4. 4.⏰ You start at 4:00 PM. Homework takes 45 minutes, then project work takes 35 minutes. When will you finish? (a) 5:35 PM (b) 4:45 PM (c) 4:35 PM (d) 5:20 PM
  5. 5.Which of these is poor project planning? (a) keeping spare days (b) no task list (c) listing tasks first (d) checking progress weekly
  6. 6.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
  7. 7.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) break it into steps (c) wait for help (d) give up
  8. 8.Which of these is poor project planning? (a) listing tasks first (b) breaking work into steps (c) starting on the last day (d) keeping spare days
  9. 9.True or false: “starting early” is good project planning. (a) True (b) False
  10. 10.True or false: “no spare time” is good project planning. (a) False (b) True
  11. 11.Which of these is poor project planning? (a) breaking work into steps (b) checking progress weekly (c) hard part first (d) forgetting the due date
  12. 12.Which of these is good project planning? (a) starting on the last day (b) doing only easy bits (c) hard part first (d) forgetting the due date
  13. 13.✅ What is a mini-deadline? (a) a date for one step (b) a holiday (c) a late fine (d) the final due date
  14. 14.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
  15. 15.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) to rest only (c) there is no need (d) for surprises
  16. 16.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) play first (c) study for the test (d) make the poster
  17. 17.True or false: “ignoring the timetable” is good project planning. (a) False (b) True
  18. 18.⏰ You start at 5:45 PM. Homework takes 40 minutes, then project work takes 15 minutes. When will you finish? (a) 6:40 PM (b) 6:00 PM (c) 6:25 PM (d) 6:55 PM
  19. 19.Which of these is good project planning? (a) guessing how long (b) ignoring the timetable (c) using a simple timetable (d) forgetting the due date
  20. 20.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  21. 21.📅 Your science model is due in 7 days. Research takes 1 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  22. 22.✂️ Your team must make 10 paper bags in 2 days, the same number each day. How many paper bags a day?
  23. 23.📅 Your art display is due in 6 days. Research takes 1 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
  24. 24.🔍 Which is the odd one out? (a) keeping spare days (b) checking progress weekly (c) setting mini-deadlines (d) one huge deadline
  25. 25.🔍 Which is the odd one out? (a) one huge deadline (b) ignoring the timetable (c) setting mini-deadlines (d) no task list
  26. 26.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
  27. 27.📅 Your science model is due in 10 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  28. 28.True or false: “setting mini-deadlines” is poor project planning. (a) False (b) True
  29. 29.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) this week (c) the night before (d) in the third week
  30. 30.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
  31. 31.🔍 Which is the odd one out? (a) no task list (b) doing only easy bits (c) ignoring the timetable (d) hard part first
  32. 32.Which of these is good project planning? (a) doing only easy bits (b) guessing how long (c) no spare time (d) setting mini-deadlines
  33. 33.📅 Your maths exhibit is due in 11 days. Research takes 1 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  34. 34.📅 Your school play is due in 13 days. Research takes 4 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  35. 35.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
  36. 36.Which of these is good project planning? (a) doing only easy bits (b) starting on the last day (c) no task list (d) breaking work into steps
  37. 37.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  38. 38.📅 Your eco-club poster is due in 8 days. Research takes 2 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
  39. 39.📅 Your maths exhibit is due in 8 days. Research takes 3 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  40. 40.⏰ You start at 3:45 PM. Homework takes 35 minutes, then project work takes 40 minutes. When will you finish? (a) 4:25 PM (b) 5:00 PM (c) 5:15 PM (d) 4:20 PM

Answer key

  1. keeping spare days
  2. guessing how long
  3. 3
  4. 5:20 PM
  5. no task list
  6. good planning
  7. break it into steps
  8. starting on the last day
  9. True
  10. False
  11. forgetting the due date
  12. hard part first
  13. a date for one step
  14. good planning
  15. for surprises
  16. study for the test
  17. False
  18. 6:40 PM
  19. using a simple timetable
  20. good planning
  21. 3
  22. 5
  23. 1
  24. one huge deadline
  25. setting mini-deadlines
  26. good planning
  27. 5
  28. False
  29. this week
  30. good planning
  31. hard part first
  32. setting mini-deadlines
  33. 2
  34. 1
  35. poor planning
  36. breaking work into steps
  37. good planning
  38. 1
  39. 1
  40. 5:00 PM

Free leadership lessons, practice and worksheets at talentjr.in/leadership-skills-for-students