Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.⏰ You start at 3:00 PM. Homework takes 30 minutes, then project work takes 15 minutes. When will you finish? (a) 3:45 PM (b) 3:30 PM (c) 4:00 PM (d) 3:15 PM
- 2.📅 Your eco-club poster is due in 12 days. Research takes 2 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 3.Which of these is poor project planning? (a) setting mini-deadlines (b) keeping spare days (c) forgetting the due date (d) starting early
- 4.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 5.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 6.📅 Your art display is due in 12 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 7.Which of these is good project planning? (a) starting on the last day (b) no task list (c) setting mini-deadlines (d) one huge deadline
- 8.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 9.✂️ Your team must make 36 bookmarks in 6 days, the same number each day. How many bookmarks a day?
- 10.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
- 11.🔍 Which is the odd one out? (a) setting mini-deadlines (b) hard part first (c) breaking work into steps (d) no task list
- 12.⏰ You start at 3:15 PM. Homework takes 40 minutes, then project work takes 35 minutes. When will you finish? (a) 3:50 PM (b) 3:55 PM (c) 4:30 PM (d) 4:45 PM
- 13.📅 Your history chart is due in 9 days. Research takes 2 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 14.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) to start late (c) there is no need (d) for surprises
- 15.Which of these is poor project planning? (a) hard part first (b) setting mini-deadlines (c) guessing how long (d) breaking work into steps
- 16.Which of these is good project planning? (a) ignoring the timetable (b) keeping spare days (c) forgetting the due date (d) doing only easy bits
- 17.✅ What is a mini-deadline? (a) a late fine (b) a holiday (c) a date for one step (d) the final due date
- 18.True or false: “doing only easy bits” is good project planning. (a) True (b) False
- 19.✂️ Your team must make 54 thank-you cards in 6 days, the same number each day. How many thank-you cards a day?
- 20.🧩 A big project feels scary. What should you do first? (a) give up (b) do it all at once (c) break it into steps (d) wait for help
- 21.⏰ You start at 5:00 PM. Homework takes 40 minutes, then project work takes 35 minutes. When will you finish? (a) 6:30 PM (b) 6:15 PM (c) 5:35 PM (d) 5:40 PM
- 22.🔍 Which is the odd one out? (a) starting on the last day (b) setting mini-deadlines (c) no task list (d) ignoring the timetable
- 23.True or false: “no spare time” is good project planning. (a) False (b) True
- 24.⏰ You start at 4:45 PM. Homework takes 35 minutes, then project work takes 15 minutes. When will you finish? (a) 5:00 PM (b) 5:20 PM (c) 5:50 PM (d) 5:35 PM
- 25.True or false: “starting early” is poor project planning. (a) True (b) False
- 26.⏰ You start at 3:15 PM. Homework takes 20 minutes, then project work takes 15 minutes. When will you finish? (a) 3:35 PM (b) 4:05 PM (c) 3:30 PM (d) 3:50 PM
- 27.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 28.True or false: “keeping spare days” is good project planning. (a) False (b) True
- 29.Which of these is good project planning? (a) starting early (b) no spare time (c) guessing how long (d) doing only easy bits
- 30.🔍 Which is the odd one out? (a) one huge deadline (b) starting on the last day (c) listing tasks first (d) no task list
- 31.🔍 Which is the odd one out? (a) checking progress weekly (b) keeping spare days (c) starting on the last day (d) starting early
- 32.True or false: “using a simple timetable” is good project planning. (a) True (b) False
- 33.✂️ Your team must make 24 posters in 3 days, the same number each day. How many posters a day?
- 34.📅 Your art display is due in 7 days. Research takes 2 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 35.📅 Your science model is due in 12 days. Research takes 3 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 36.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) this week (c) in the third week (d) the night before
- 37.True or false: “hard part first” is poor project planning. (a) True (b) False
- 38.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) make the poster (b) study for the test (c) play first (d) neither
- 39.True or false: “one huge deadline” is poor project planning. (a) True (b) False
- 40.Which of these is good project planning? (a) ignoring the timetable (b) hard part first (c) no spare time (d) one huge deadline
Answer key
- 3:45 PM
- 2
- forgetting the due date
- good planning
- good planning
- 5
- setting mini-deadlines
- good planning
- 6
- poor planning
- no task list
- 4:30 PM
- 1
- for surprises
- guessing how long
- keeping spare days
- a date for one step
- False
- 9
- break it into steps
- 6:15 PM
- setting mini-deadlines
- False
- 5:35 PM
- False
- 3:50 PM
- poor planning
- True
- starting early
- listing tasks first
- starting on the last day
- True
- 8
- 2
- 4
- this week
- False
- study for the test
- True
- hard part first