Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 929 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.True or false: “listing tasks first” is poor project planning. (a) True (b) False
  2. 2.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
  3. 3.Which of these is poor project planning? (a) forgetting the due date (b) starting early (c) using a simple timetable (d) hard part first
  4. 4.🔍 Which is the odd one out? (a) one huge deadline (b) no task list (c) no spare time (d) using a simple timetable
  5. 5.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  6. 6.🔍 Which is the odd one out? (a) one huge deadline (b) starting early (c) no spare time (d) no task list
  7. 7.⏰ You start at 4:00 PM. Homework takes 45 minutes, then project work takes 25 minutes. When will you finish? (a) 5:25 PM (b) 5:10 PM (c) 4:45 PM (d) 4:25 PM
  8. 8.🔍 Which is the odd one out? (a) setting mini-deadlines (b) forgetting the due date (c) no task list (d) starting on the last day
  9. 9.True or false: “starting on the last day” is good project planning. (a) False (b) True
  10. 10.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
  11. 11.⏰ You start at 3:30 PM. Homework takes 40 minutes, then project work takes 30 minutes. When will you finish? (a) 4:00 PM (b) 4:10 PM (c) 4:55 PM (d) 4:40 PM
  12. 12.🔍 Which is the odd one out? (a) listing tasks first (b) hard part first (c) checking progress weekly (d) ignoring the timetable
  13. 13.Which of these is poor project planning? (a) checking progress weekly (b) one huge deadline (c) hard part first (d) starting early
  14. 14.Which of these is good project planning? (a) no task list (b) checking progress weekly (c) no spare time (d) forgetting the due date
  15. 15.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
  16. 16.Which of these is poor project planning? (a) using a simple timetable (b) setting mini-deadlines (c) no task list (d) breaking work into steps
  17. 17.True or false: “doing only easy bits” is good project planning. (a) False (b) True
  18. 18.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) the night before (c) this week (d) after it is due
  19. 19.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
  20. 20.✂️ Your team must make 16 paper flowers in 2 days, the same number each day. How many paper flowers a day?
  21. 21.Which of these is poor project planning? (a) keeping spare days (b) setting mini-deadlines (c) using a simple timetable (d) ignoring the timetable
  22. 22.🔍 Which is the odd one out? (a) no spare time (b) forgetting the due date (c) hard part first (d) no task list
  23. 23.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) for surprises (c) to start late (d) there is no need
  24. 24.🔍 Which is the odd one out? (a) guessing how long (b) starting early (c) setting mini-deadlines (d) listing tasks first
  25. 25.Which of these is good project planning? (a) guessing how long (b) forgetting the due date (c) ignoring the timetable (d) keeping spare days
  26. 26.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
  27. 27.🔍 Which is the odd one out? (a) setting mini-deadlines (b) keeping spare days (c) hard part first (d) no task list
  28. 28.Which of these is good project planning? (a) setting mini-deadlines (b) ignoring the timetable (c) one huge deadline (d) starting on the last day
  29. 29.🧩 A big project feels scary. What should you do first? (a) wait for help (b) do it all at once (c) break it into steps (d) give up
  30. 30.Which of these is poor project planning? (a) hard part first (b) checking progress weekly (c) breaking work into steps (d) starting on the last day
  31. 31.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  32. 32.True or false: “starting early” is poor project planning. (a) True (b) False
  33. 33.📅 Your eco-club poster is due in 15 days. Research takes 3 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  34. 34.Which of these is good project planning? (a) one huge deadline (b) no spare time (c) starting on the last day (d) starting early
  35. 35.⏰ You start at 5:15 PM. Homework takes 30 minutes, then project work takes 15 minutes. When will you finish? (a) 5:30 PM (b) 6:15 PM (c) 6:00 PM (d) 5:45 PM
  36. 36.📅 Your school play is due in 9 days. Research takes 2 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
  37. 37.📅 Your eco-club poster is due in 12 days. Research takes 3 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
  38. 38.📅 Your art display is due in 10 days. Research takes 3 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
  39. 39.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) neither (c) play first (d) make the poster
  40. 40.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning

Answer key

  1. False
  2. good planning
  3. forgetting the due date
  4. using a simple timetable
  5. good planning
  6. starting early
  7. 5:10 PM
  8. setting mini-deadlines
  9. False
  10. good planning
  11. 4:40 PM
  12. ignoring the timetable
  13. one huge deadline
  14. checking progress weekly
  15. True
  16. no task list
  17. False
  18. this week
  19. good planning
  20. 8
  21. ignoring the timetable
  22. hard part first
  23. for surprises
  24. guessing how long
  25. keeping spare days
  26. False
  27. no task list
  28. setting mini-deadlines
  29. break it into steps
  30. starting on the last day
  31. good planning
  32. False
  33. 5
  34. starting early
  35. 6:00 PM
  36. 1
  37. 3
  38. 1
  39. study for the test
  40. poor planning