Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 931 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) wait for help (c) break it into steps (d) give up
  2. 2.Which of these is poor project planning? (a) listing tasks first (b) hard part first (c) using a simple timetable (d) no spare time
  3. 3.🔍 Which is the odd one out? (a) no task list (b) checking progress weekly (c) starting early (d) keeping spare days
  4. 4.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
  5. 5.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  6. 6.🔍 Which is the odd one out? (a) starting on the last day (b) ignoring the timetable (c) keeping spare days (d) doing only easy bits
  7. 7.🔍 Which is the odd one out? (a) setting mini-deadlines (b) starting early (c) listing tasks first (d) doing only easy bits
  8. 8.Which of these is poor project planning? (a) setting mini-deadlines (b) breaking work into steps (c) checking progress weekly (d) starting on the last day
  9. 9.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) study for the test (c) neither (d) make the poster
  10. 10.🔍 Which is the odd one out? (a) ignoring the timetable (b) using a simple timetable (c) no task list (d) starting on the last day
  11. 11.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
  12. 12.🔍 Which is the odd one out? (a) setting mini-deadlines (b) listing tasks first (c) starting early (d) no spare time
  13. 13.🔍 Which is the odd one out? (a) no spare time (b) no task list (c) setting mini-deadlines (d) starting on the last day
  14. 14.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) for surprises (c) to rest only (d) there is no need
  15. 15.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
  16. 16.🔍 Which is the odd one out? (a) starting on the last day (b) guessing how long (c) hard part first (d) ignoring the timetable
  17. 17.📅 Your art display is due in 13 days. Research takes 4 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
  18. 18.Which of these is good project planning? (a) doing only easy bits (b) checking progress weekly (c) ignoring the timetable (d) starting on the last day
  19. 19.Which of these is good project planning? (a) ignoring the timetable (b) guessing how long (c) no task list (d) setting mini-deadlines
  20. 20.✂️ Your team must make 16 bookmarks in 4 days, the same number each day. How many bookmarks a day?
  21. 21.✅ What is a mini-deadline? (a) a holiday (b) a late fine (c) a date for one step (d) the final due date
  22. 22.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
  23. 23.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
  24. 24.Which of these is poor project planning? (a) keeping spare days (b) breaking work into steps (c) hard part first (d) ignoring the timetable
  25. 25.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
  26. 26.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) this week (c) in the third week (d) the night before
  27. 27.Which of these is good project planning? (a) hard part first (b) one huge deadline (c) no spare time (d) doing only easy bits
  28. 28.📅 Your history chart is due in 11 days. Research takes 3 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
  29. 29.Which of these is good project planning? (a) doing only easy bits (b) starting early (c) no spare time (d) guessing how long
  30. 30.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
  31. 31.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
  32. 32.True or false: “one huge deadline” is good project planning. (a) True (b) False
  33. 33.✂️ Your team must make 30 thank-you cards in 6 days, the same number each day. How many thank-you cards a day?
  34. 34.🔍 Which is the odd one out? (a) starting early (b) using a simple timetable (c) breaking work into steps (d) ignoring the timetable
  35. 35.True or false: “doing only easy bits” is good project planning. (a) True (b) False
  36. 36.True or false: “starting on the last day” is good project planning. (a) False (b) True
  37. 37.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
  38. 38.True or false: “forgetting the due date” is good project planning. (a) False (b) True
  39. 39.⏰ You start at 5:15 PM. Homework takes 40 minutes, then project work takes 25 minutes. When will you finish? (a) 6:35 PM (b) 5:40 PM (c) 5:55 PM (d) 6:20 PM
  40. 40.📅 Your class magazine is due in 15 days. Research takes 4 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?

Answer key

  1. break it into steps
  2. no spare time
  3. no task list
  4. poor planning
  5. good planning
  6. keeping spare days
  7. doing only easy bits
  8. starting on the last day
  9. study for the test
  10. using a simple timetable
  11. good planning
  12. no spare time
  13. setting mini-deadlines
  14. for surprises
  15. good planning
  16. hard part first
  17. 4
  18. checking progress weekly
  19. setting mini-deadlines
  20. 4
  21. a date for one step
  22. poor planning
  23. poor planning
  24. ignoring the timetable
  25. False
  26. this week
  27. hard part first
  28. 4
  29. starting early
  30. good planning
  31. poor planning
  32. False
  33. 5
  34. ignoring the timetable
  35. False
  36. False
  37. poor planning
  38. False
  39. 6:20 PM
  40. 5