Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 941 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Your history chart is due in 12 days. Research takes 4 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  2. 2.🔍 Which is the odd one out? (a) ignoring the timetable (b) guessing how long (c) forgetting the due date (d) keeping spare days
  3. 3.True or false: “no spare time” is good project planning. (a) True (b) False
  4. 4.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to rest only (c) to start late (d) for surprises
  5. 5.Which of these is poor project planning? (a) setting mini-deadlines (b) ignoring the timetable (c) breaking work into steps (d) keeping spare days
  6. 6.True or false: “hard part first” is poor project planning. (a) False (b) True
  7. 7.⏰ You start at 4:30 PM. Homework takes 25 minutes, then project work takes 40 minutes. When will you finish? (a) 4:55 PM (b) 5:35 PM (c) 5:50 PM (d) 5:10 PM
  8. 8.📅 Your maths exhibit is due in 9 days. Research takes 2 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  9. 9.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) study for the test (c) play first (d) make the poster
  10. 10.True or false: “starting on the last day” is good project planning. (a) False (b) True
  11. 11.🧩 A big project feels scary. What should you do first? (a) wait for help (b) do it all at once (c) give up (d) break it into steps
  12. 12.🔍 Which is the odd one out? (a) one huge deadline (b) setting mini-deadlines (c) no spare time (d) doing only easy bits
  13. 13.🔍 Which is the odd one out? (a) using a simple timetable (b) one huge deadline (c) breaking work into steps (d) setting mini-deadlines
  14. 14.True or false: “no task list” is poor project planning. (a) True (b) False
  15. 15.Which of these is good project planning? (a) guessing how long (b) breaking work into steps (c) forgetting the due date (d) no task list
  16. 16.Which of these is good project planning? (a) one huge deadline (b) starting on the last day (c) setting mini-deadlines (d) guessing how long
  17. 17.Which of these is poor project planning? (a) checking progress weekly (b) guessing how long (c) listing tasks first (d) setting mini-deadlines
  18. 18.✅ What is a mini-deadline? (a) a late fine (b) a holiday (c) a date for one step (d) the final due date
  19. 19.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
  20. 20.🔍 Which is the odd one out? (a) using a simple timetable (b) setting mini-deadlines (c) doing only easy bits (d) checking progress weekly
  21. 21.✂️ Your team must make 16 thank-you cards in 4 days, the same number each day. How many thank-you cards a day?
  22. 22.True or false: “using a simple timetable” is poor project planning. (a) True (b) False
  23. 23.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
  24. 24.Which of these is good project planning? (a) starting on the last day (b) no task list (c) forgetting the due date (d) checking progress weekly
  25. 25.True or false: “doing only easy bits” is poor project planning. (a) True (b) False
  26. 26.True or false: “starting early” is good project planning. (a) False (b) True
  27. 27.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) the night before (c) this week (d) in the third week
  28. 28.Which of these is poor project planning? (a) no task list (b) keeping spare days (c) hard part first (d) listing tasks first
  29. 29.⏰ You start at 5:30 PM. Homework takes 45 minutes, then project work takes 40 minutes. When will you finish? (a) 6:55 PM (b) 7:10 PM (c) 6:10 PM (d) 6:15 PM
  30. 30.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
  31. 31.🔍 Which is the odd one out? (a) listing tasks first (b) starting early (c) keeping spare days (d) no spare time
  32. 32.⏰ You start at 4:30 PM. Homework takes 35 minutes, then project work takes 20 minutes. When will you finish? (a) 5:40 PM (b) 5:25 PM (c) 5:05 PM (d) 4:50 PM
  33. 33.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
  34. 34.True or false: “starting on the last day” is poor project planning. (a) False (b) True
  35. 35.🔍 Which is the odd one out? (a) guessing how long (b) no spare time (c) doing only easy bits (d) breaking work into steps
  36. 36.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
  37. 37.Which of these is poor project planning? (a) forgetting the due date (b) checking progress weekly (c) listing tasks first (d) breaking work into steps
  38. 38.Which of these is good project planning? (a) forgetting the due date (b) doing only easy bits (c) keeping spare days (d) starting on the last day
  39. 39.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
  40. 40.🔍 Which is the odd one out? (a) checking progress weekly (b) setting mini-deadlines (c) breaking work into steps (d) no task list

Answer key

  1. 1
  2. keeping spare days
  3. False
  4. for surprises
  5. ignoring the timetable
  6. False
  7. 5:35 PM
  8. 4
  9. study for the test
  10. False
  11. break it into steps
  12. setting mini-deadlines
  13. one huge deadline
  14. True
  15. breaking work into steps
  16. setting mini-deadlines
  17. guessing how long
  18. a date for one step
  19. False
  20. doing only easy bits
  21. 4
  22. False
  23. poor planning
  24. checking progress weekly
  25. True
  26. True
  27. this week
  28. no task list
  29. 6:55 PM
  30. good planning
  31. no spare time
  32. 5:25 PM
  33. good planning
  34. True
  35. breaking work into steps
  36. poor planning
  37. forgetting the due date
  38. keeping spare days
  39. good planning
  40. no task list