Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 945 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  2. 2.🔍 Which is the odd one out? (a) setting mini-deadlines (b) hard part first (c) forgetting the due date (d) listing tasks first
  3. 3.True or false: “ignoring the timetable” is good project planning. (a) True (b) False
  4. 4.True or false: “guessing how long” is poor project planning. (a) True (b) False
  5. 5.True or false: “forgetting the due date” is poor project planning. (a) False (b) True
  6. 6.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) to rest only (c) for surprises (d) there is no need
  7. 7.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) study for the test (d) play first
  8. 8.Which of these is poor project planning? (a) breaking work into steps (b) using a simple timetable (c) doing only easy bits (d) hard part first
  9. 9.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
  10. 10.🔍 Which is the odd one out? (a) breaking work into steps (b) hard part first (c) listing tasks first (d) starting on the last day
  11. 11.Which of these is good project planning? (a) starting early (b) no spare time (c) ignoring the timetable (d) guessing how long
  12. 12.True or false: “starting early” is good project planning. (a) False (b) True
  13. 13.Which of these is good project planning? (a) using a simple timetable (b) guessing how long (c) no task list (d) no spare time
  14. 14.⏰ You start at 3:15 PM. Homework takes 40 minutes, then project work takes 30 minutes. When will you finish? (a) 4:40 PM (b) 3:55 PM (c) 4:25 PM (d) 3:45 PM
  15. 15.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) this week (c) in the third week (d) the night before
  16. 16.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) break it into steps (c) give up (d) wait for help
  17. 17.Which of these is poor project planning? (a) starting on the last day (b) checking progress weekly (c) breaking work into steps (d) setting mini-deadlines
  18. 18.Which of these is poor project planning? (a) setting mini-deadlines (b) listing tasks first (c) forgetting the due date (d) breaking work into steps
  19. 19.📅 Your maths exhibit is due in 10 days. Research takes 3 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
  20. 20.✂️ Your team must make 16 bookmarks in 2 days, the same number each day. How many bookmarks a day?
  21. 21.🔍 Which is the odd one out? (a) starting early (b) guessing how long (c) listing tasks first (d) keeping spare days
  22. 22.Which of these is good project planning? (a) doing only easy bits (b) checking progress weekly (c) forgetting the due date (d) one huge deadline
  23. 23.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
  24. 24.⏰ You start at 3:30 PM. Homework takes 30 minutes, then project work takes 30 minutes. When will you finish? (a) 4:30 PM (b) 4:00 PM (c) 4:45 PM
  25. 25.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
  26. 26.Which of these is poor project planning? (a) checking progress weekly (b) no task list (c) starting early (d) listing tasks first
  27. 27.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
  28. 28.True or false: “starting early” is poor project planning. (a) False (b) True
  29. 29.⏰ You start at 5:00 PM. Homework takes 40 minutes, then project work takes 40 minutes. When will you finish? (a) 6:20 PM (b) 5:40 PM (c) 6:35 PM
  30. 30.⏰ You start at 3:15 PM. Homework takes 20 minutes, then project work takes 35 minutes. When will you finish? (a) 3:50 PM (b) 4:25 PM (c) 4:10 PM (d) 3:35 PM
  31. 31.Which of these is poor project planning? (a) no spare time (b) keeping spare days (c) breaking work into steps (d) hard part first
  32. 32.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
  33. 33.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
  34. 34.⏰ You start at 5:30 PM. Homework takes 25 minutes, then project work takes 20 minutes. When will you finish? (a) 5:50 PM (b) 6:30 PM (c) 5:55 PM (d) 6:15 PM
  35. 35.⏰ You start at 5:15 PM. Homework takes 30 minutes, then project work takes 25 minutes. When will you finish? (a) 6:10 PM (b) 5:45 PM (c) 5:40 PM (d) 6:25 PM
  36. 36.📅 Your science model is due in 8 days. Research takes 2 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
  37. 37.🔍 Which is the odd one out? (a) setting mini-deadlines (b) starting on the last day (c) no spare time (d) ignoring the timetable
  38. 38.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
  39. 39.🔍 Which is the odd one out? (a) doing only easy bits (b) breaking work into steps (c) starting on the last day (d) no spare time
  40. 40.📅 Your history chart is due in 10 days. Research takes 1 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?

Answer key

  1. good planning
  2. forgetting the due date
  3. False
  4. True
  5. True
  6. for surprises
  7. study for the test
  8. doing only easy bits
  9. False
  10. starting on the last day
  11. starting early
  12. True
  13. using a simple timetable
  14. 4:25 PM
  15. this week
  16. break it into steps
  17. starting on the last day
  18. forgetting the due date
  19. 1
  20. 8
  21. guessing how long
  22. checking progress weekly
  23. True
  24. 4:30 PM
  25. poor planning
  26. no task list
  27. good planning
  28. False
  29. 6:20 PM
  30. 4:10 PM
  31. no spare time
  32. good planning
  33. poor planning
  34. 6:15 PM
  35. 6:10 PM
  36. 1
  37. setting mini-deadlines
  38. poor planning
  39. breaking work into steps
  40. 3