Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 95 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🔍 Which is the odd one out? (a) hard part first (b) starting on the last day (c) checking progress weekly (d) setting mini-deadlines
  2. 2.📅 Your class magazine is due in 14 days. Research takes 1 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  3. 3.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
  4. 4.Which of these is good project planning? (a) no task list (b) hard part first (c) doing only easy bits (d) one huge deadline
  5. 5.Which of these is good project planning? (a) doing only easy bits (b) no task list (c) no spare time (d) checking progress weekly
  6. 6.Which of these is poor project planning? (a) breaking work into steps (b) using a simple timetable (c) starting on the last day (d) setting mini-deadlines
  7. 7.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  8. 8.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) the night before (c) this week (d) in the third week
  9. 9.Which of these is poor project planning? (a) no spare time (b) using a simple timetable (c) checking progress weekly (d) hard part first
  10. 10.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
  11. 11.📅 Your maths exhibit is due in 10 days. Research takes 2 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
  12. 12.🔍 Which is the odd one out? (a) keeping spare days (b) setting mini-deadlines (c) checking progress weekly (d) ignoring the timetable
  13. 13.Which of these is good project planning? (a) forgetting the due date (b) keeping spare days (c) ignoring the timetable (d) guessing how long
  14. 14.True or false: “breaking work into steps” is good project planning. (a) False (b) True
  15. 15.🔍 Which is the odd one out? (a) ignoring the timetable (b) doing only easy bits (c) checking progress weekly (d) forgetting the due date
  16. 16.True or false: “forgetting the due date” is good project planning. (a) False (b) True
  17. 17.Which of these is good project planning? (a) listing tasks first (b) one huge deadline (c) starting on the last day (d) no task list
  18. 18.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) do it all at once (c) give up (d) wait for help
  19. 19.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
  20. 20.📅 Your school play is due in 10 days. Research takes 1 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  21. 21.🔍 Which is the odd one out? (a) hard part first (b) forgetting the due date (c) breaking work into steps (d) setting mini-deadlines
  22. 22.Which of these is good project planning? (a) one huge deadline (b) no task list (c) starting early (d) guessing how long
  23. 23.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  24. 24.Which of these is poor project planning? (a) hard part first (b) breaking work into steps (c) setting mini-deadlines (d) guessing how long
  25. 25.🔍 Which is the odd one out? (a) listing tasks first (b) doing only easy bits (c) no spare time (d) no task list
  26. 26.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a date for one step (d) a holiday
  27. 27.True or false: “hard part first” is poor project planning. (a) True (b) False
  28. 28.📅 Your maths exhibit is due in 14 days. Research takes 4 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  29. 29.📅 Your science model is due in 10 days. Research takes 2 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  30. 30.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
  31. 31.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
  32. 32.Which of these is poor project planning? (a) listing tasks first (b) starting early (c) keeping spare days (d) ignoring the timetable
  33. 33.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  34. 34.📅 Your science model is due in 16 days. Research takes 4 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  35. 35.Which of these is good project planning? (a) forgetting the due date (b) using a simple timetable (c) no task list (d) starting on the last day
  36. 36.Which of these is poor project planning? (a) using a simple timetable (b) hard part first (c) doing only easy bits (d) checking progress weekly
  37. 37.True or false: “listing tasks first” is good project planning. (a) False (b) True
  38. 38.✂️ Your team must make 10 paper flowers in 2 days, the same number each day. How many paper flowers a day?
  39. 39.True or false: “starting early” is poor project planning. (a) False (b) True
  40. 40.True or false: “checking progress weekly” is good project planning. (a) True (b) False

Answer key

  1. starting on the last day
  2. 5
  3. False
  4. hard part first
  5. checking progress weekly
  6. starting on the last day
  7. good planning
  8. this week
  9. no spare time
  10. poor planning
  11. 2
  12. ignoring the timetable
  13. keeping spare days
  14. True
  15. checking progress weekly
  16. False
  17. listing tasks first
  18. break it into steps
  19. poor planning
  20. 2
  21. forgetting the due date
  22. starting early
  23. good planning
  24. guessing how long
  25. listing tasks first
  26. a date for one step
  27. False
  28. 5
  29. 4
  30. poor planning
  31. poor planning
  32. ignoring the timetable
  33. good planning
  34. 4
  35. using a simple timetable
  36. doing only easy bits
  37. True
  38. 5
  39. False
  40. True