Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 956 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.✂️ Your team must make 12 thank-you cards in 3 days, the same number each day. How many thank-you cards a day?
  2. 2.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  3. 3.🔍 Which is the odd one out? (a) doing only easy bits (b) starting early (c) hard part first (d) setting mini-deadlines
  4. 4.Which of these is poor project planning? (a) listing tasks first (b) breaking work into steps (c) using a simple timetable (d) forgetting the due date
  5. 5.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
  6. 6.Which of these is good project planning? (a) starting on the last day (b) doing only easy bits (c) one huge deadline (d) checking progress weekly
  7. 7.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  8. 8.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
  9. 9.🔍 Which is the odd one out? (a) listing tasks first (b) starting on the last day (c) keeping spare days (d) using a simple timetable
  10. 10.Which of these is poor project planning? (a) using a simple timetable (b) breaking work into steps (c) no task list (d) starting early
  11. 11.Which of these is good project planning? (a) ignoring the timetable (b) forgetting the due date (c) starting on the last day (d) setting mini-deadlines
  12. 12.True or false: “forgetting the due date” is good project planning. (a) True (b) False
  13. 13.True or false: “checking progress weekly” is good project planning. (a) True (b) False
  14. 14.Which of these is poor project planning? (a) ignoring the timetable (b) listing tasks first (c) breaking work into steps (d) starting early
  15. 15.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) give up (c) do it all at once (d) wait for help
  16. 16.True or false: “hard part first” is good project planning. (a) False (b) True
  17. 17.🔍 Which is the odd one out? (a) one huge deadline (b) hard part first (c) no spare time (d) starting on the last day
  18. 18.True or false: “ignoring the timetable” is good project planning. (a) False (b) True
  19. 19.Which of these is poor project planning? (a) starting early (b) no spare time (c) hard part first (d) keeping spare days
  20. 20.True or false: “no spare time” is poor project planning. (a) False (b) True
  21. 21.✅ What is a mini-deadline? (a) a date for one step (b) the final due date (c) a late fine (d) a holiday
  22. 22.Which of these is good project planning? (a) forgetting the due date (b) using a simple timetable (c) guessing how long (d) no task list
  23. 23.🔍 Which is the odd one out? (a) no spare time (b) doing only easy bits (c) no task list (d) listing tasks first
  24. 24.True or false: “starting early” is poor project planning. (a) False (b) True
  25. 25.🔍 Which is the odd one out? (a) forgetting the due date (b) using a simple timetable (c) doing only easy bits (d) ignoring the timetable
  26. 26.🔍 Which is the odd one out? (a) one huge deadline (b) guessing how long (c) setting mini-deadlines (d) starting on the last day
  27. 27.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
  28. 28.Which of these is poor project planning? (a) doing only easy bits (b) listing tasks first (c) starting early (d) using a simple timetable
  29. 29.⏰ You start at 5:15 PM. Homework takes 45 minutes, then project work takes 25 minutes. When will you finish? (a) 6:25 PM (b) 6:00 PM (c) 6:40 PM (d) 5:40 PM
  30. 30.✂️ Your team must make 36 name badges in 4 days, the same number each day. How many name badges a day?
  31. 31.Which of these is good project planning? (a) forgetting the due date (b) ignoring the timetable (c) doing only easy bits (d) breaking work into steps
  32. 32.🔍 Which is the odd one out? (a) setting mini-deadlines (b) checking progress weekly (c) forgetting the due date (d) listing tasks first
  33. 33.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
  34. 34.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) make the poster (b) study for the test (c) neither (d) play first
  35. 35.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
  36. 36.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
  37. 37.🔍 Which is the odd one out? (a) checking progress weekly (b) ignoring the timetable (c) doing only easy bits (d) no task list
  38. 38.✂️ Your team must make 54 name badges in 6 days, the same number each day. How many name badges a day?
  39. 39.True or false: “hard part first” is poor project planning. (a) False (b) True
  40. 40.Which of these is good project planning? (a) ignoring the timetable (b) guessing how long (c) listing tasks first (d) no task list

Answer key

  1. 4
  2. good planning
  3. doing only easy bits
  4. forgetting the due date
  5. good planning
  6. checking progress weekly
  7. good planning
  8. good planning
  9. starting on the last day
  10. no task list
  11. setting mini-deadlines
  12. False
  13. True
  14. ignoring the timetable
  15. break it into steps
  16. True
  17. hard part first
  18. False
  19. no spare time
  20. True
  21. a date for one step
  22. using a simple timetable
  23. listing tasks first
  24. False
  25. using a simple timetable
  26. setting mini-deadlines
  27. good planning
  28. doing only easy bits
  29. 6:25 PM
  30. 9
  31. breaking work into steps
  32. forgetting the due date
  33. good planning
  34. study for the test
  35. poor planning
  36. good planning
  37. checking progress weekly
  38. 9
  39. False
  40. listing tasks first