Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 965 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.Which of these is good project planning? (a) ignoring the timetable (b) no task list (c) breaking work into steps (d) no spare time
  2. 2.✅ What is a mini-deadline? (a) a holiday (b) a date for one step (c) a late fine (d) the final due date
  3. 3.Which of these is good project planning? (a) listing tasks first (b) ignoring the timetable (c) no task list (d) starting on the last day
  4. 4.🔍 Which is the odd one out? (a) starting early (b) guessing how long (c) breaking work into steps (d) setting mini-deadlines
  5. 5.🔍 Which is the odd one out? (a) guessing how long (b) no task list (c) no spare time (d) checking progress weekly
  6. 6.Which of these is poor project planning? (a) no task list (b) listing tasks first (c) hard part first (d) checking progress weekly
  7. 7.✂️ Your team must make 21 paper flowers in 3 days, the same number each day. How many paper flowers a day?
  8. 8.Which of these is good project planning? (a) using a simple timetable (b) no task list (c) ignoring the timetable (d) forgetting the due date
  9. 9.✂️ Your team must make 27 paper flowers in 3 days, the same number each day. How many paper flowers a day?
  10. 10.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) neither (c) play first (d) make the poster
  11. 11.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) break it into steps (c) wait for help (d) give up
  12. 12.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) to start late (c) for surprises (d) there is no need
  13. 13.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
  14. 14.🔍 Which is the odd one out? (a) no task list (b) doing only easy bits (c) forgetting the due date (d) keeping spare days
  15. 15.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
  16. 16.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) this week (d) the night before
  17. 17.📅 Your science model is due in 16 days. Research takes 4 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  18. 18.Which of these is poor project planning? (a) breaking work into steps (b) starting early (c) guessing how long (d) setting mini-deadlines
  19. 19.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
  20. 20.Which of these is poor project planning? (a) listing tasks first (b) using a simple timetable (c) starting on the last day (d) starting early
  21. 21.True or false: “starting early” is good project planning. (a) True (b) False
  22. 22.✂️ Your team must make 12 paper bags in 4 days, the same number each day. How many paper bags a day?
  23. 23.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
  24. 24.🔍 Which is the odd one out? (a) breaking work into steps (b) starting on the last day (c) using a simple timetable (d) keeping spare days
  25. 25.🔍 Which is the odd one out? (a) starting early (b) checking progress weekly (c) doing only easy bits (d) setting mini-deadlines
  26. 26.Which of these is good project planning? (a) keeping spare days (b) forgetting the due date (c) no spare time (d) one huge deadline
  27. 27.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
  28. 28.⏰ You start at 5:15 PM. Homework takes 20 minutes, then project work takes 35 minutes. When will you finish? (a) 5:50 PM (b) 5:35 PM (c) 6:10 PM (d) 6:25 PM
  29. 29.✂️ Your team must make 10 posters in 5 days, the same number each day. How many posters a day?
  30. 30.📅 Your maths exhibit is due in 13 days. Research takes 4 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
  31. 31.⏰ You start at 5:30 PM. Homework takes 40 minutes, then project work takes 40 minutes. When will you finish? (a) 7:05 PM (b) 6:50 PM (c) 6:10 PM
  32. 32.Which of these is poor project planning? (a) forgetting the due date (b) breaking work into steps (c) hard part first (d) setting mini-deadlines
  33. 33.Which of these is good project planning? (a) starting early (b) doing only easy bits (c) no spare time (d) no task list
  34. 34.🔍 Which is the odd one out? (a) starting early (b) breaking work into steps (c) keeping spare days (d) no spare time
  35. 35.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
  36. 36.Which of these is poor project planning? (a) starting early (b) one huge deadline (c) using a simple timetable (d) checking progress weekly
  37. 37.✂️ Your team must make 10 thank-you cards in 5 days, the same number each day. How many thank-you cards a day?
  38. 38.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
  39. 39.🔍 Which is the odd one out? (a) setting mini-deadlines (b) forgetting the due date (c) using a simple timetable (d) keeping spare days
  40. 40.📅 Your maths exhibit is due in 12 days. Research takes 2 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?

Answer key

  1. breaking work into steps
  2. a date for one step
  3. listing tasks first
  4. guessing how long
  5. checking progress weekly
  6. no task list
  7. 7
  8. using a simple timetable
  9. 9
  10. study for the test
  11. break it into steps
  12. for surprises
  13. poor planning
  14. keeping spare days
  15. good planning
  16. this week
  17. 5
  18. guessing how long
  19. good planning
  20. starting on the last day
  21. True
  22. 3
  23. poor planning
  24. starting on the last day
  25. doing only easy bits
  26. keeping spare days
  27. good planning
  28. 6:10 PM
  29. 2
  30. 2
  31. 6:50 PM
  32. forgetting the due date
  33. starting early
  34. no spare time
  35. good planning
  36. one huge deadline
  37. 2
  38. good planning
  39. forgetting the due date
  40. 2