Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 968 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.✅ What is a mini-deadline? (a) a holiday (b) a date for one step (c) the final due date (d) a late fine
  2. 2.⏰ You start at 4:15 PM. Homework takes 25 minutes, then project work takes 40 minutes. When will you finish? (a) 5:20 PM (b) 5:35 PM (c) 4:55 PM (d) 4:40 PM
  3. 3.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) neither (c) study for the test (d) make the poster
  4. 4.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
  5. 5.🔍 Which is the odd one out? (a) hard part first (b) guessing how long (c) ignoring the timetable (d) doing only easy bits
  6. 6.✂️ Your team must make 36 posters in 6 days, the same number each day. How many posters a day?
  7. 7.True or false: “one huge deadline” is good project planning. (a) True (b) False
  8. 8.🔍 Which is the odd one out? (a) guessing how long (b) listing tasks first (c) doing only easy bits (d) no task list
  9. 9.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
  10. 10.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
  11. 11.Which of these is poor project planning? (a) listing tasks first (b) using a simple timetable (c) breaking work into steps (d) guessing how long
  12. 12.🔍 Which is the odd one out? (a) doing only easy bits (b) breaking work into steps (c) listing tasks first (d) starting early
  13. 13.🔍 Which is the odd one out? (a) hard part first (b) starting early (c) starting on the last day (d) checking progress weekly
  14. 14.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
  15. 15.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) this week (c) the night before (d) in the third week
  16. 16.Which of these is poor project planning? (a) ignoring the timetable (b) keeping spare days (c) hard part first (d) breaking work into steps
  17. 17.⏰ You start at 4:45 PM. Homework takes 30 minutes, then project work takes 35 minutes. When will you finish? (a) 5:50 PM (b) 5:20 PM (c) 6:05 PM (d) 5:15 PM
  18. 18.Which of these is good project planning? (a) using a simple timetable (b) forgetting the due date (c) guessing how long (d) no spare time
  19. 19.Which of these is good project planning? (a) guessing how long (b) starting on the last day (c) no task list (d) checking progress weekly
  20. 20.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
  21. 21.True or false: “keeping spare days” is good project planning. (a) False (b) True
  22. 22.🔍 Which is the odd one out? (a) guessing how long (b) breaking work into steps (c) checking progress weekly (d) starting early
  23. 23.True or false: “listing tasks first” is poor project planning. (a) False (b) True
  24. 24.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) give up (c) break it into steps (d) wait for help
  25. 25.Which of these is good project planning? (a) doing only easy bits (b) no spare time (c) one huge deadline (d) listing tasks first
  26. 26.📅 Your history chart is due in 12 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  27. 27.True or false: “checking progress weekly” is poor project planning. (a) False (b) True
  28. 28.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
  29. 29.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
  30. 30.True or false: “ignoring the timetable” is poor project planning. (a) False (b) True
  31. 31.⏰ You start at 3:15 PM. Homework takes 25 minutes, then project work takes 25 minutes. When will you finish? (a) 4:20 PM (b) 3:40 PM (c) 4:05 PM
  32. 32.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
  33. 33.📅 Your history chart is due in 8 days. Research takes 2 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
  34. 34.Which of these is good project planning? (a) keeping spare days (b) ignoring the timetable (c) guessing how long (d) doing only easy bits
  35. 35.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
  36. 36.📅 Your school play is due in 7 days. Research takes 1 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  37. 37.✂️ Your team must make 12 paper flowers in 4 days, the same number each day. How many paper flowers a day?
  38. 38.True or false: “keeping spare days” is poor project planning. (a) False (b) True
  39. 39.Which of these is good project planning? (a) no task list (b) starting on the last day (c) forgetting the due date (d) breaking work into steps
  40. 40.Which of these is poor project planning? (a) keeping spare days (b) breaking work into steps (c) hard part first (d) starting on the last day

Answer key

  1. a date for one step
  2. 5:20 PM
  3. study for the test
  4. poor planning
  5. hard part first
  6. 6
  7. False
  8. listing tasks first
  9. good planning
  10. False
  11. guessing how long
  12. doing only easy bits
  13. starting on the last day
  14. good planning
  15. this week
  16. ignoring the timetable
  17. 5:50 PM
  18. using a simple timetable
  19. checking progress weekly
  20. poor planning
  21. True
  22. guessing how long
  23. False
  24. break it into steps
  25. listing tasks first
  26. 5
  27. False
  28. good planning
  29. good planning
  30. True
  31. 4:05 PM
  32. poor planning
  33. 1
  34. keeping spare days
  35. poor planning
  36. 3
  37. 3
  38. False
  39. breaking work into steps
  40. starting on the last day