Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
- 2.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 3.True or false: “checking progress weekly” is good project planning. (a) False (b) True
- 4.✂️ Your team must make 12 bookmarks in 3 days, the same number each day. How many bookmarks a day?
- 5.⏳ Why keep a spare day or two before the deadline? (a) for surprises (b) to rest only (c) there is no need (d) to start late
- 6.⏰ You start at 4:30 PM. Homework takes 20 minutes, then project work takes 40 minutes. When will you finish? (a) 4:50 PM (b) 5:30 PM (c) 5:45 PM (d) 5:10 PM
- 7.Which of these is poor project planning? (a) breaking work into steps (b) keeping spare days (c) listing tasks first (d) ignoring the timetable
- 8.⏰ You start at 3:30 PM. Homework takes 20 minutes, then project work takes 35 minutes. When will you finish? (a) 4:05 PM (b) 3:50 PM (c) 4:25 PM (d) 4:40 PM
- 9.True or false: “guessing how long” is poor project planning. (a) True (b) False
- 10.Which of these is poor project planning? (a) starting early (b) setting mini-deadlines (c) one huge deadline (d) keeping spare days
- 11.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) the night before (c) this week (d) after it is due
- 12.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 13.🔍 Which is the odd one out? (a) breaking work into steps (b) ignoring the timetable (c) listing tasks first (d) starting early
- 14.True or false: “starting on the last day” is poor project planning. (a) False (b) True
- 15.✂️ Your team must make 6 name badges in 2 days, the same number each day. How many name badges a day?
- 16.Which of these is poor project planning? (a) no spare time (b) listing tasks first (c) starting early (d) breaking work into steps
- 17.Which of these is good project planning? (a) one huge deadline (b) no task list (c) guessing how long (d) hard part first
- 18.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 19.📅 Your eco-club poster is due in 7 days. Research takes 1 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 20.Which of these is good project planning? (a) starting on the last day (b) forgetting the due date (c) ignoring the timetable (d) listing tasks first
- 21.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 22.🔍 Which is the odd one out? (a) forgetting the due date (b) hard part first (c) starting on the last day (d) one huge deadline
- 23.🔍 Which is the odd one out? (a) one huge deadline (b) no spare time (c) listing tasks first (d) starting on the last day
- 24.🔍 Which is the odd one out? (a) no task list (b) checking progress weekly (c) breaking work into steps (d) listing tasks first
- 25.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
- 26.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) neither (c) study for the test (d) make the poster
- 27.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) wait for help (c) do it all at once (d) give up
- 28.🔍 Which is the odd one out? (a) setting mini-deadlines (b) hard part first (c) breaking work into steps (d) starting on the last day
- 29.True or false: “setting mini-deadlines” is good project planning. (a) True (b) False
- 30.🔍 Which is the odd one out? (a) listing tasks first (b) using a simple timetable (c) breaking work into steps (d) no spare time
- 31.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 32.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 33.True or false: “starting early” is poor project planning. (a) True (b) False
- 34.✂️ Your team must make 4 thank-you cards in 2 days, the same number each day. How many thank-you cards a day?
- 35.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 36.📅 Your science model is due in 10 days. Research takes 3 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 37.🔍 Which is the odd one out? (a) one huge deadline (b) using a simple timetable (c) listing tasks first (d) setting mini-deadlines
- 38.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 39.📅 Your science model is due in 10 days. Research takes 1 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 40.✅ What is a mini-deadline? (a) a holiday (b) a date for one step (c) the final due date (d) a late fine
Answer key
- poor planning
- False
- True
- 4
- for surprises
- 5:30 PM
- ignoring the timetable
- 4:25 PM
- True
- one huge deadline
- this week
- poor planning
- ignoring the timetable
- True
- 3
- no spare time
- hard part first
- poor planning
- 2
- listing tasks first
- good planning
- hard part first
- listing tasks first
- no task list
- False
- study for the test
- break it into steps
- starting on the last day
- True
- no spare time
- good planning
- good planning
- False
- 2
- good planning
- 3
- one huge deadline
- good planning
- 4
- a date for one step