Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) make the poster (c) play first (d) neither
- 2.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 3.📅 Your class magazine is due in 10 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 4.⏰ You start at 5:15 PM. Homework takes 25 minutes, then project work takes 20 minutes. When will you finish? (a) 5:40 PM (b) 5:35 PM (c) 6:15 PM (d) 6:00 PM
- 5.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) to rest only (c) for surprises (d) there is no need
- 6.📅 Your science model is due in 8 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 7.🔍 Which is the odd one out? (a) guessing how long (b) setting mini-deadlines (c) forgetting the due date (d) no spare time
- 8.✂️ Your team must make 36 paper flowers in 6 days, the same number each day. How many paper flowers a day?
- 9.True or false: “ignoring the timetable” is poor project planning. (a) True (b) False
- 10.✂️ Your team must make 16 paper bags in 2 days, the same number each day. How many paper bags a day?
- 11.🔍 Which is the odd one out? (a) starting early (b) setting mini-deadlines (c) ignoring the timetable (d) using a simple timetable
- 12.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
- 13.🔍 Which is the odd one out? (a) starting on the last day (b) listing tasks first (c) starting early (d) hard part first
- 14.🧩 A big project feels scary. What should you do first? (a) wait for help (b) break it into steps (c) give up (d) do it all at once
- 15.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
- 16.✂️ Your team must make 24 paper bags in 4 days, the same number each day. How many paper bags a day?
- 17.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 18.📅 Your science model is due in 6 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 19.Which of these is good project planning? (a) guessing how long (b) doing only easy bits (c) keeping spare days (d) no task list
- 20.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) after it is due (d) the night before
- 21.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
- 22.Which of these is good project planning? (a) no task list (b) listing tasks first (c) one huge deadline (d) forgetting the due date
- 23.📅 Your class magazine is due in 13 days. Research takes 2 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 24.True or false: “breaking work into steps” is poor project planning. (a) True (b) False
- 25.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
- 26.✅ What is a mini-deadline? (a) the final due date (b) a date for one step (c) a late fine (d) a holiday
- 27.True or false: “using a simple timetable” is poor project planning. (a) True (b) False
- 28.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 29.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 30.📅 Your art display is due in 10 days. Research takes 2 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 31.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 32.📅 Your maths exhibit is due in 15 days. Research takes 4 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 33.⏰ You start at 5:00 PM. Homework takes 25 minutes, then project work takes 25 minutes. When will you finish? (a) 5:50 PM (b) 5:25 PM (c) 6:05 PM
- 34.Which of these is good project planning? (a) breaking work into steps (b) one huge deadline (c) ignoring the timetable (d) forgetting the due date
- 35.🔍 Which is the odd one out? (a) no task list (b) starting on the last day (c) keeping spare days (d) one huge deadline
- 36.Which of these is poor project planning? (a) checking progress weekly (b) breaking work into steps (c) using a simple timetable (d) forgetting the due date
- 37.🔍 Which is the odd one out? (a) no task list (b) no spare time (c) guessing how long (d) using a simple timetable
- 38.🔍 Which is the odd one out? (a) no spare time (b) breaking work into steps (c) listing tasks first (d) setting mini-deadlines
- 39.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
- 40.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
Answer key
- study for the test
- good planning
- 5
- 6:00 PM
- for surprises
- 3
- setting mini-deadlines
- 6
- True
- 8
- ignoring the timetable
- False
- starting on the last day
- break it into steps
- True
- 6
- good planning
- 1
- keeping spare days
- this week
- poor planning
- listing tasks first
- 5
- False
- poor planning
- a date for one step
- False
- good planning
- good planning
- 2
- good planning
- 5
- 5:50 PM
- breaking work into steps
- keeping spare days
- forgetting the due date
- using a simple timetable
- no spare time
- poor planning
- poor planning