Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Arjun can finish a job in 15 days and Manav in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 2.Zoya can finish a job in 22 days and Meera in 16 days. Zoya works alone for 11 days and then stops. Meera finishes the rest. How many days does Meera take?
- 3.Arjun works three times as fast as Kavya. Together they finish a job in 6 days. How many days would Kavya take alone?
- 4.Rahul can finish a job in 15 days and Zoya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Aarav can finish a job in 8 days and Ishaan in 4 days. Aarav works alone for 4 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 6.Pooja works twice as fast as Isha. Together they finish a job in 4 days. How many days would Isha take alone?
- 7.Manav works three times as fast as Karan. Together they finish a job in 4 days. How many days would Karan take alone?
- 8.Meera can finish a job in 6 days and Aditya in 13 days. What fraction of the job do they finish if they work together for 2 days? =
- 9.Meera can finish a job in 16 days and Vivaan in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 10.Nisha can finish a job in 2 days and Manav in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Aarav can finish a job in 11 days and Vivaan in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 12.Aarav and Manav together finish a job in 3 days. Aarav alone takes 4 days. How many days would Manav take alone?
- 13.Rohan can finish a job in 6 days and Aarav in 10 days. What fraction of the job do they finish if they work together for 2 days? =
- 14.Arjun works twice as fast as Vivaan. Together they finish a job in 4 days. How many days would Vivaan take alone?
- 15.Diya can finish a job in 19 days and Rohan in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 16.Isha can finish a job in 12 days and Kavya in 30 days. Isha works alone for 10 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 17.Saanvi works three times as fast as Rohan. Together they finish a job in 2 days. How many days would Rohan take alone?
- 18.Arjun works twice as fast as Rohan. Together they finish a job in 11 days. How many days would Rohan take alone?
- 19.Isha and Nisha together finish a job in 2 days. Isha alone takes 4 days. How many days would Nisha take alone?
- 20.Pooja works three times as fast as Aarav. Together they finish a job in 5 days. How many days would Aarav take alone?
- 21.Nisha can finish a job in 6 days and Isha in 13 days. What fraction of the job do they finish if they work together for 1 day? =
- 22.Kavya and Meera together finish a job in 6 days. Kavya alone takes 8 days. How many days would Meera take alone?
- 23.Zoya works three times as fast as Meera. Together they finish a job in 3 days. How many days would Meera take alone?
- 24.Farhan works three times as fast as Kavya. Together they finish a job in 5 days. How many days would Kavya take alone?
- 25.Vivaan works three times as fast as Ananya. Together they finish a job in 7 days. How many days would Ananya take alone?
- 26.Meera can finish a job in 2 days and Pooja in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Vivaan can finish a job in 14 days and Meera in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Rohan and Nisha together finish a job in 2 days. Rohan alone takes 6 days. How many days would Nisha take alone?
- 29.Diya can finish a job in 2 days and Tara in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Vivaan can finish a job in 25 days and Aarav in 5 days. Vivaan works alone for 20 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 31.Saanvi can finish a job in 10 days and Isha in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Kabir works twice as fast as Pooja. Together they finish a job in 11 days. How many days would Pooja take alone?
- 33.Ishaan and Rahul together finish a job in 5 days. Ishaan alone takes 6 days. How many days would Rahul take alone?
- 34.Meera can finish a job in 20 days and Karan in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Rohan works twice as fast as Karan. Together they finish a job in 9 days. How many days would Karan take alone?
- 36.Karan can finish a job in 10 days and Diya in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 37.Aarav can finish a job in 4 days and Farhan in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 38.Kavya can finish a job in 10 days and Diya in 8 days. Kavya works alone for 5 days and then stops. Diya finishes the rest. How many days does Diya take?
- 39.Karan and Ananya together finish a job in 4 days. Karan alone takes 5 days. How many days would Ananya take alone?
- 40.Isha can finish a job in 20 days and Farhan in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 30/7
- 8
- 24
- 5/2
- 2
- 12
- 16
- 19/39
- 7/16
- 10/7
- 15/22
- 12
- 8/15
- 12
- 31/76
- 5
- 8
- 33
- 4
- 20
- 19/78
- 24
- 12
- 20
- 28
- 7/4
- 7/4
- 3
- 16/9
- 1
- 6
- 33
- 30
- 140/17
- 27
- 10/3
- 9/20
- 4
- 20
- 15/2