Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Kabir and Vivaan together finish a job in 6 days. Kabir alone takes 8 days. How many days would Vivaan take alone?
- 2.Aditya can finish a job in 6 days and Ishaan in 12 days. Aditya works alone for 4 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 3.Arjun can finish a job in 13 days and Aarav in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Farhan can finish a job in 9 days and Diya in 8 days. What fraction of the job do they finish if they work together for 2 days? =
- 5.Meera can finish a job in 9 days and Sneha in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Ishaan works twice as fast as Rahul. Together they finish a job in 7 days. How many days would Rahul take alone?
- 7.Isha can finish a job in 5 days and Aarav in 25 days. Isha works alone for 2 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 8.Saanvi can finish a job in 7 days and Rahul in 9 days. What fraction of the job do they finish if they work together for 3 days? =
- 9.Nisha can finish a job in 7 days and Kavya in 21 days. Nisha works alone for 1 day and then stops. Kavya finishes the rest. How many days does Kavya take?
- 10.Rahul can finish a job in 5 days and Saanvi in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 11.Saanvi works three times as fast as Pooja. Together they finish a job in 3 days. How many days would Pooja take alone?
- 12.Pooja can finish a job in 20 days and Sneha in 10 days. Pooja works alone for 12 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 13.Meera can finish a job in 4 days and Tara in 20 days. What fraction of the job do they finish if they work together for 1 day? =
- 14.Diya works three times as fast as Kavya. Together they finish a job in 10 days. How many days would Kavya take alone?
- 15.Rohan can finish a job in 4 days and Kavya in 13 days. What fraction of the job do they finish if they work together for 1 day? =
- 16.Diya works three times as fast as Dev. Together they finish a job in 12 days. How many days would Dev take alone?
- 17.Rohan and Diya together finish a job in 3 days. Rohan alone takes 4 days. How many days would Diya take alone?
- 18.Dev can finish a job in 13 days and Meera in 6 days. What fraction of the job do they finish if they work together for 1 day? =
- 19.Saanvi and Ishaan together finish a job in 2 days. Saanvi alone takes 3 days. How many days would Ishaan take alone?
- 20.Priya can finish a job in 19 days and Kabir in 12 days. What fraction of the job do they finish if they work together for 2 days? =
- 21.Rohan and Vivaan together finish a job in 5 days. Rohan alone takes 10 days. How many days would Vivaan take alone?
- 22.Diya works twice as fast as Ananya. Together they finish a job in 4 days. How many days would Ananya take alone?
- 23.Tara and Manav together finish a job in 12 days. Tara alone takes 15 days. How many days would Manav take alone?
- 24.Meera can finish a job in 15 days and Rahul in 10 days. Meera works alone for 9 days and then stops. Rahul finishes the rest. How many days does Rahul take?
- 25.Kavya can finish a job in 8 days and Aditya in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 26.Zoya can finish a job in 18 days and Ishaan in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Aditya can finish a job in 13 days and Aarav in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Tara works twice as fast as Karan. Together they finish a job in 2 days. How many days would Karan take alone?
- 29.Arjun and Karan together finish a job in 2 days. Arjun alone takes 4 days. How many days would Karan take alone?
- 30.Rohan and Meera together finish a job in 3 days. Rohan alone takes 6 days. How many days would Meera take alone?
- 31.Rohan and Vivaan together finish a job in 10 days. Rohan alone takes 12 days. How many days would Vivaan take alone?
- 32.Kavya works twice as fast as Vivaan. Together they finish a job in 3 days. How many days would Vivaan take alone?
- 33.Ishaan and Aarav together finish a job in 7 days. Ishaan alone takes 8 days. How many days would Aarav take alone?
- 34.Tara and Rohan together finish a job in 6 days. Tara alone takes 10 days. How many days would Rohan take alone?
- 35.Kavya works three times as fast as Priya. Together they finish a job in 11 days. How many days would Priya take alone?
- 36.Rahul can finish a job in 20 days and Vivaan in 28 days. Rahul works alone for 15 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 37.Tara and Rahul together finish a job in 2 days. Tara alone takes 4 days. How many days would Rahul take alone?
- 38.Kavya and Meera together finish a job in 2 days. Kavya alone takes 3 days. How many days would Meera take alone?
- 39.Karan and Aarav together finish a job in 2 days. Karan alone takes 4 days. How many days would Aarav take alone?
- 40.Rahul can finish a job in 11 days and Aditya in 22 days. Rahul works alone for 3 days and then stops. Aditya finishes the rest. How many days does Aditya take?
Answer key
- 24
- 4
- 208/29
- 17/36
- 171/28
- 21
- 15
- 16/21
- 18
- 8/15
- 12
- 4
- 3/10
- 40
- 17/52
- 48
- 12
- 19/78
- 6
- 31/114
- 10
- 12
- 60
- 4
- 15/28
- 72/13
- 234/31
- 6
- 4
- 6
- 60
- 9
- 56
- 15
- 44
- 7
- 4
- 6
- 4
- 16