Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Isha can finish a job in 10 days and Karan in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 2.Diya can finish a job in 6 days and Ishaan in 14 days. What fraction of the job do they finish if they work together for 1 day? =
- 3.Saanvi and Dev together finish a job in 2 days. Saanvi alone takes 4 days. How many days would Dev take alone?
- 4.Ananya can finish a job in 4 days and Aarav in 20 days. Ananya works alone for 1 day and then stops. Aarav finishes the rest. How many days does Aarav take?
- 5.Zoya can finish a job in 5 days and Saanvi in 15 days. Zoya works alone for 3 days and then stops. Saanvi finishes the rest. How many days does Saanvi take?
- 6.Manav and Diya together finish a job in 7 days. Manav alone takes 8 days. How many days would Diya take alone?
- 7.Pooja and Zoya together finish a job in 6 days. Pooja alone takes 12 days. How many days would Zoya take alone?
- 8.Kabir can finish a job in 18 days and Ananya in 14 days. Kabir works alone for 9 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 9.Sneha works three times as fast as Karan. Together they finish a job in 9 days. How many days would Karan take alone?
- 10.Aarav can finish a job in 5 days and Sneha in 10 days. Aarav works alone for 3 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 11.Vivaan and Rohan together finish a job in 2 days. Vivaan alone takes 3 days. How many days would Rohan take alone?
- 12.Manav can finish a job in 11 days and Ananya in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 13.Vivaan can finish a job in 7 days and Saanvi in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Priya works twice as fast as Sneha. Together they finish a job in 4 days. How many days would Sneha take alone?
- 15.Arjun works three times as fast as Sneha. Together they finish a job in 7 days. How many days would Sneha take alone?
- 16.Kavya can finish a job in 17 days and Nisha in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 17.Kavya works three times as fast as Priya. Together they finish a job in 11 days. How many days would Priya take alone?
- 18.Farhan and Kabir together finish a job in 5 days. Farhan alone takes 6 days. How many days would Kabir take alone?
- 19.Karan works three times as fast as Rahul. Together they finish a job in 8 days. How many days would Rahul take alone?
- 20.Ananya can finish a job in 8 days and Saanvi in 20 days. Ananya works alone for 2 days and then stops. Saanvi finishes the rest. How many days does Saanvi take?
- 21.Zoya can finish a job in 14 days and Arjun in 17 days. What fraction of the job do they finish if they work together for 1 day? =
- 22.Pooja can finish a job in 5 days and Tara in 12 days. What fraction of the job do they finish if they work together for 2 days? =
- 23.Ananya and Aarav together finish a job in 3 days. Ananya alone takes 4 days. How many days would Aarav take alone?
- 24.Sneha can finish a job in 6 days and Ishaan in 14 days. What fraction of the job do they finish if they work together for 3 days? =
- 25.Kavya and Arjun together finish a job in 10 days. Kavya alone takes 12 days. How many days would Arjun take alone?
- 26.Farhan can finish a job in 8 days and Pooja in 12 days. What fraction of the job do they finish if they work together for 1 day? =
- 27.Priya works three times as fast as Aditya. Together they finish a job in 5 days. How many days would Aditya take alone?
- 28.Manav can finish a job in 6 days and Dev in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Nisha works twice as fast as Aditya. Together they finish a job in 8 days. How many days would Aditya take alone?
- 30.Karan can finish a job in 7 days and Diya in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Aditya works three times as fast as Kabir. Together they finish a job in 8 days. How many days would Kabir take alone?
- 32.Diya can finish a job in 6 days and Priya in 11 days. What fraction of the job do they finish if they work together for 1 day? =
- 33.Priya works twice as fast as Ananya. Together they finish a job in 4 days. How many days would Ananya take alone?
- 34.Kabir can finish a job in 15 days and Nisha in 5 days. Kabir works alone for 3 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 35.Tara can finish a job in 4 days and Sneha in 28 days. Tara works alone for 2 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 36.Tara works twice as fast as Isha. Together they finish a job in 6 days. How many days would Isha take alone?
- 37.Rohan can finish a job in 19 days and Pooja in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Ananya can finish a job in 10 days and Diya in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Kavya works three times as fast as Tara. Together they finish a job in 8 days. How many days would Tara take alone?
- 40.Farhan can finish a job in 12 days and Arjun in 13 days. What fraction of the job do they finish if they work together for 2 days? =
Answer key
- 7/20
- 5/21
- 4
- 15
- 6
- 56
- 12
- 7
- 36
- 4
- 6
- 26/165
- 119/24
- 12
- 28
- 27/170
- 44
- 30
- 32
- 15
- 31/238
- 17/30
- 12
- 5/7
- 60
- 5/24
- 20
- 9/2
- 24
- 56/15
- 32
- 17/66
- 12
- 4
- 14
- 18
- 171/28
- 90/19
- 32
- 25/78