Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Priya and Diya together finish a job in 8 days. Priya alone takes 10 days. How many days would Diya take alone?
- 2.Isha works twice as fast as Zoya. Together they finish a job in 4 days. How many days would Zoya take alone?
- 3.Farhan can finish a job in 7 days and Karan in 18 days. What fraction of the job do they finish if they work together for 2 days? =
- 4.Manav can finish a job in 5 days and Ananya in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 5.Arjun works three times as fast as Isha. Together they finish a job in 7 days. How many days would Isha take alone?
- 6.Kabir can finish a job in 17 days and Meera in 12 days. What fraction of the job do they finish if they work together for 3 days? =
- 7.Rohan can finish a job in 10 days and Manav in 4 days. Rohan works alone for 5 days and then stops. Manav finishes the rest. How many days does Manav take?
- 8.Meera and Aarav together finish a job in 14 days. Meera alone takes 18 days. How many days would Aarav take alone?
- 9.Diya can finish a job in 7 days and Tara in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Nisha can finish a job in 14 days and Vivaan in 10 days. What fraction of the job do they finish if they work together for 3 days? =
- 11.Kabir can finish a job in 11 days and Isha in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Kabir can finish a job in 7 days and Zoya in 14 days. Kabir works alone for 4 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 13.Aarav and Farhan together finish a job in 4 days. Aarav alone takes 20 days. How many days would Farhan take alone?
- 14.Diya works twice as fast as Saanvi. Together they finish a job in 5 days. How many days would Saanvi take alone?
- 15.Nisha can finish a job in 6 days and Zoya in 5 days. What fraction of the job do they finish if they work together for 2 days? =
- 16.Dev and Karan together finish a job in 7 days. Dev alone takes 8 days. How many days would Karan take alone?
- 17.Rohan works twice as fast as Kavya. Together they finish a job in 2 days. How many days would Kavya take alone?
- 18.Tara can finish a job in 14 days and Manav in 7 days. Tara works alone for 10 days and then stops. Manav finishes the rest. How many days does Manav take?
- 19.Arjun works twice as fast as Diya. Together they finish a job in 10 days. How many days would Diya take alone?
- 20.Isha can finish a job in 6 days and Saanvi in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 21.Rohan can finish a job in 19 days and Tara in 20 days. What fraction of the job do they finish if they work together for 1 day? =
- 22.Sneha can finish a job in 16 days and Ananya in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Kabir can finish a job in 27 days and Ananya in 9 days. Kabir works alone for 6 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 24.Tara works twice as fast as Dev. Together they finish a job in 2 days. How many days would Dev take alone?
- 25.Meera can finish a job in 12 days and Aarav in 9 days. What fraction of the job do they finish if they work together for 1 day? =
- 26.Tara can finish a job in 19 days and Kabir in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Farhan works twice as fast as Pooja. Together they finish a job in 6 days. How many days would Pooja take alone?
- 28.Kabir and Karan together finish a job in 14 days. Kabir alone takes 18 days. How many days would Karan take alone?
- 29.Meera and Zoya together finish a job in 10 days. Meera alone takes 30 days. How many days would Zoya take alone?
- 30.Pooja can finish a job in 8 days and Nisha in 16 days. Pooja works alone for 6 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 31.Aarav can finish a job in 16 days and Saanvi in 20 days. What fraction of the job do they finish if they work together for 3 days? =
- 32.Arjun and Farhan together finish a job in 21 days. Arjun alone takes 30 days. How many days would Farhan take alone?
- 33.Kabir can finish a job in 16 days and Zoya in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Vivaan can finish a job in 12 days and Aarav in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 35.Ishaan and Tara together finish a job in 4 days. Ishaan alone takes 20 days. How many days would Tara take alone?
- 36.Diya can finish a job in 11 days and Ishaan in 14 days. What fraction of the job do they finish if they work together for 1 day? =
- 37.Nisha can finish a job in 16 days and Saanvi in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Nisha can finish a job in 3 days and Arjun in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Nisha and Dev together finish a job in 3 days. Nisha alone takes 4 days. How many days would Dev take alone?
- 40.Kabir works twice as fast as Rohan. Together they finish a job in 7 days. How many days would Rohan take alone?
Answer key
- 40
- 12
- 25/63
- 17/20
- 28
- 29/68
- 2
- 63
- 84/19
- 18/35
- 110/21
- 6
- 5
- 15
- 11/15
- 56
- 6
- 2
- 30
- 13/21
- 39/380
- 176/27
- 7
- 6
- 7/36
- 285/34
- 18
- 63
- 15
- 4
- 27/80
- 70
- 112/15
- 17/60
- 5
- 25/154
- 48/19
- 12/5
- 12
- 21