Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Tara can finish a job in 8 days and Rohan in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 2.Aditya and Vivaan together finish a job in 5 days. Aditya alone takes 30 days. How many days would Vivaan take alone?
- 3.Pooja and Ananya together finish a job in 3 days. Pooja alone takes 6 days. How many days would Ananya take alone?
- 4.Rohan and Meera together finish a job in 6 days. Rohan alone takes 10 days. How many days would Meera take alone?
- 5.Manav can finish a job in 7 days and Zoya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Meera can finish a job in 5 days and Pooja in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Meera works three times as fast as Saanvi. Together they finish a job in 10 days. How many days would Saanvi take alone?
- 8.Rahul and Arjun together finish a job in 2 days. Rahul alone takes 3 days. How many days would Arjun take alone?
- 9.Aditya and Aarav together finish a job in 6 days. Aditya alone takes 7 days. How many days would Aarav take alone?
- 10.Arjun works twice as fast as Dev. Together they finish a job in 9 days. How many days would Dev take alone?
- 11.Priya and Vivaan together finish a job in 5 days. Priya alone takes 10 days. How many days would Vivaan take alone?
- 12.Zoya can finish a job in 9 days and Priya in 7 days. What fraction of the job do they finish if they work together for 1 day? =
- 13.Saanvi and Kabir together finish a job in 4 days. Saanvi alone takes 8 days. How many days would Kabir take alone?
- 14.Diya can finish a job in 10 days and Aarav in 25 days. Diya works alone for 6 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 15.Meera can finish a job in 3 days and Karan in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Ishaan can finish a job in 4 days and Kabir in 8 days. Ishaan works alone for 2 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 17.Farhan can finish a job in 5 days and Meera in 15 days. Farhan works alone for 4 days and then stops. Meera finishes the rest. How many days does Meera take?
- 18.Ananya can finish a job in 27 days and Meera in 18 days. Ananya works alone for 12 days and then stops. Meera finishes the rest. How many days does Meera take?
- 19.Rohan works twice as fast as Meera. Together they finish a job in 5 days. How many days would Meera take alone?
- 20.Isha can finish a job in 16 days and Ananya in 11 days. What fraction of the job do they finish if they work together for 1 day? =
- 21.Zoya can finish a job in 5 days and Pooja in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Nisha and Tara together finish a job in 2 days. Nisha alone takes 3 days. How many days would Tara take alone?
- 23.Zoya can finish a job in 9 days and Aarav in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 24.Kabir can finish a job in 15 days and Aditya in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Dev and Priya together finish a job in 10 days. Dev alone takes 20 days. How many days would Priya take alone?
- 26.Diya can finish a job in 15 days and Rahul in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Diya can finish a job in 5 days and Sneha in 30 days. Diya works alone for 4 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 28.Dev can finish a job in 7 days and Rohan in 9 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Farhan can finish a job in 5 days and Sneha in 30 days. Farhan works alone for 3 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 30.Rohan can finish a job in 12 days and Meera in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Kabir can finish a job in 4 days and Ishaan in 16 days. Kabir works alone for 1 day and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 32.Pooja works twice as fast as Priya. Together they finish a job in 3 days. How many days would Priya take alone?
- 33.Diya works twice as fast as Zoya. Together they finish a job in 6 days. How many days would Zoya take alone?
- 34.Rohan can finish a job in 19 days and Zoya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Karan can finish a job in 18 days and Kabir in 10 days. Karan works alone for 9 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 36.Manav can finish a job in 5 days and Zoya in 15 days. Manav works alone for 2 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 37.Kavya can finish a job in 8 days and Zoya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 38.Diya works twice as fast as Tara. Together they finish a job in 2 days. How many days would Tara take alone?
- 39.Nisha can finish a job in 13 days and Zoya in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 40.Aarav and Kabir together finish a job in 6 days. Aarav alone takes 24 days. How many days would Kabir take alone?
Answer key
- 7/12
- 6
- 6
- 15
- 14/9
- 40/13
- 40
- 6
- 42
- 27
- 10
- 16/63
- 8
- 10
- 39/16
- 4
- 3
- 10
- 15
- 27/176
- 95/24
- 6
- 144/25
- 20/3
- 20
- 60/19
- 6
- 63/16
- 12
- 156/25
- 12
- 9
- 18
- 38/21
- 5
- 9
- 8/5
- 6
- 195/28
- 8