Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Farhan can finish a job in 11 days and Kavya in 9 days. What fraction of the job do they finish if they work together for 2 days? =
- 2.Ananya can finish a job in 10 days and Rohan in 12 days. Ananya works alone for 5 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 3.Aarav works three times as fast as Kavya. Together they finish a job in 3 days. How many days would Kavya take alone?
- 4.Vivaan and Dev together finish a job in 10 days. Vivaan alone takes 15 days. How many days would Dev take alone?
- 5.Ishaan and Aarav together finish a job in 10 days. Ishaan alone takes 12 days. How many days would Aarav take alone?
- 6.Vivaan can finish a job in 6 days and Kabir in 21 days. Vivaan works alone for 4 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 7.Aditya can finish a job in 25 days and Tara in 5 days. Aditya works alone for 15 days and then stops. Tara finishes the rest. How many days does Tara take?
- 8.Ananya and Isha together finish a job in 3 days. Ananya alone takes 4 days. How many days would Isha take alone?
- 9.Diya can finish a job in 17 days and Kavya in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 10.Diya and Sneha together finish a job in 6 days. Diya alone takes 7 days. How many days would Sneha take alone?
- 11.Isha can finish a job in 15 days and Priya in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 12.Saanvi can finish a job in 19 days and Farhan in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 13.Ishaan can finish a job in 6 days and Nisha in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Dev can finish a job in 12 days and Ananya in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Karan can finish a job in 9 days and Meera in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 16.Meera and Sneha together finish a job in 3 days. Meera alone takes 4 days. How many days would Sneha take alone?
- 17.Farhan and Tara together finish a job in 4 days. Farhan alone takes 5 days. How many days would Tara take alone?
- 18.Dev can finish a job in 13 days and Ishaan in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 19.Nisha can finish a job in 18 days and Kavya in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 20.Aarav and Vivaan together finish a job in 2 days. Aarav alone takes 4 days. How many days would Vivaan take alone?
- 21.Sneha can finish a job in 7 days and Arjun in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 22.Meera can finish a job in 14 days and Karan in 11 days. What fraction of the job do they finish if they work together for 2 days? =
- 23.Sneha can finish a job in 20 days and Diya in 19 days. What fraction of the job do they finish if they work together for 3 days? =
- 24.Meera can finish a job in 17 days and Sneha in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Dev can finish a job in 24 days and Farhan in 6 days. Dev works alone for 20 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 26.Aditya can finish a job in 5 days and Priya in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Ishaan works twice as fast as Rohan. Together they finish a job in 5 days. How many days would Rohan take alone?
- 28.Aditya and Ishaan together finish a job in 4 days. Aditya alone takes 5 days. How many days would Ishaan take alone?
- 29.Arjun works three times as fast as Manav. Together they finish a job in 7 days. How many days would Manav take alone?
- 30.Diya and Ishaan together finish a job in 3 days. Diya alone takes 6 days. How many days would Ishaan take alone?
- 31.Manav can finish a job in 19 days and Tara in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Isha can finish a job in 8 days and Meera in 12 days. Isha works alone for 2 days and then stops. Meera finishes the rest. How many days does Meera take?
- 33.Diya can finish a job in 4 days and Farhan in 28 days. Diya works alone for 3 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 34.Tara can finish a job in 15 days and Rohan in 10 days. Tara works alone for 12 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 35.Pooja and Kabir together finish a job in 14 days. Pooja alone takes 18 days. How many days would Kabir take alone?
- 36.Kabir can finish a job in 24 days and Aditya in 16 days. Kabir works alone for 18 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 37.Dev can finish a job in 10 days and Meera in 5 days. What fraction of the job do they finish if they work together for 1 day? =
- 38.Sneha can finish a job in 7 days and Rahul in 12 days. What fraction of the job do they finish if they work together for 2 days? =
- 39.Meera works three times as fast as Manav. Together they finish a job in 12 days. How many days would Manav take alone?
- 40.Aarav can finish a job in 6 days and Nisha in 17 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
Answer key
- 40/99
- 6
- 12
- 30
- 60
- 7
- 2
- 12
- 48/119
- 42
- 34/285
- 33/133
- 42/13
- 204/29
- 180/29
- 12
- 20
- 91/20
- 31/78
- 4
- 60/91
- 25/77
- 117/380
- 68/21
- 1
- 90/23
- 15
- 20
- 28
- 6
- 95/24
- 9
- 7
- 2
- 63
- 4
- 3/10
- 19/42
- 48
- 102/23