Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Karan can finish a job in 6 days and Aditya in 22 days. Karan works alone for 3 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 2.Aditya can finish a job in 6 days and Ananya in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 3.Ishaan can finish a job in 2 days and Farhan in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Dev can finish a job in 6 days and Meera in 4 days. Dev works alone for 3 days and then stops. Meera finishes the rest. How many days does Meera take?
- 5.Aditya can finish a job in 8 days and Kavya in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Tara can finish a job in 10 days and Diya in 4 days. Tara works alone for 5 days and then stops. Diya finishes the rest. How many days does Diya take?
- 7.Manav can finish a job in 5 days and Zoya in 8 days. What fraction of the job do they finish if they work together for 2 days? =
- 8.Ananya works three times as fast as Nisha. Together they finish a job in 5 days. How many days would Nisha take alone?
- 9.Ananya can finish a job in 9 days and Rahul in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Saanvi works three times as fast as Kavya. Together they finish a job in 7 days. How many days would Kavya take alone?
- 11.Farhan can finish a job in 5 days and Kavya in 30 days. Farhan works alone for 2 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 12.Aarav can finish a job in 4 days and Aditya in 12 days. Aarav works alone for 3 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 13.Aditya works three times as fast as Pooja. Together they finish a job in 9 days. How many days would Pooja take alone?
- 14.Diya can finish a job in 6 days and Karan in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 15.Karan and Dev together finish a job in 3 days. Karan alone takes 4 days. How many days would Dev take alone?
- 16.Kavya can finish a job in 9 days and Manav in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 17.Isha can finish a job in 11 days and Diya in 17 days. What fraction of the job do they finish if they work together for 1 day? =
- 18.Nisha can finish a job in 18 days and Dev in 12 days. Nisha works alone for 3 days and then stops. Dev finishes the rest. How many days does Dev take?
- 19.Isha works twice as fast as Ananya. Together they finish a job in 10 days. How many days would Ananya take alone?
- 20.Aarav and Ananya together finish a job in 4 days. Aarav alone takes 8 days. How many days would Ananya take alone?
- 21.Karan can finish a job in 13 days and Manav in 26 days. Karan works alone for 11 days and then stops. Manav finishes the rest. How many days does Manav take?
- 22.Zoya can finish a job in 8 days and Tara in 10 days. Zoya works alone for 4 days and then stops. Tara finishes the rest. How many days does Tara take?
- 23.Kabir can finish a job in 5 days and Diya in 15 days. What fraction of the job do they finish if they work together for 1 day? =
- 24.Aarav works three times as fast as Zoya. Together they finish a job in 11 days. How many days would Zoya take alone?
- 25.Manav can finish a job in 8 days and Meera in 24 days. Manav works alone for 1 day and then stops. Meera finishes the rest. How many days does Meera take?
- 26.Zoya and Rohan together finish a job in 6 days. Zoya alone takes 10 days. How many days would Rohan take alone?
- 27.Zoya can finish a job in 5 days and Aditya in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 28.Nisha works three times as fast as Pooja. Together they finish a job in 4 days. How many days would Pooja take alone?
- 29.Rohan can finish a job in 9 days and Manav in 4 days. What fraction of the job do they finish if they work together for 2 days? =
- 30.Zoya can finish a job in 9 days and Aarav in 27 days. Zoya works alone for 1 day and then stops. Aarav finishes the rest. How many days does Aarav take?
- 31.Rahul works twice as fast as Farhan. Together they finish a job in 2 days. How many days would Farhan take alone?
- 32.Nisha can finish a job in 2 days and Ananya in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 33.Sneha can finish a job in 4 days and Aarav in 20 days. Sneha works alone for 3 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 34.Arjun and Farhan together finish a job in 10 days. Arjun alone takes 15 days. How many days would Farhan take alone?
- 35.Ananya can finish a job in 4 days and Kabir in 16 days. Ananya works alone for 2 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 36.Farhan works three times as fast as Sneha. Together they finish a job in 2 days. How many days would Sneha take alone?
- 37.Meera works twice as fast as Ananya. Together they finish a job in 8 days. How many days would Ananya take alone?
- 38.Saanvi can finish a job in 7 days and Rohan in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Kavya works three times as fast as Meera. Together they finish a job in 8 days. How many days would Meera take alone?
- 40.Pooja and Nisha together finish a job in 2 days. Pooja alone takes 3 days. How many days would Nisha take alone?
Answer key
- 11
- 11/24
- 12/7
- 2
- 56/15
- 2
- 13/20
- 20
- 63/16
- 28
- 18
- 3
- 36
- 48/11
- 12
- 63/16
- 28/187
- 10
- 30
- 8
- 4
- 5
- 4/15
- 44
- 21
- 15
- 35/12
- 16
- 13/18
- 24
- 6
- 26/15
- 5
- 30
- 8
- 8
- 24
- 35/12
- 32
- 6