Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Sneha works twice as fast as Diya. Together they finish a job in 3 days. How many days would Diya take alone?
- 2.Diya and Ananya together finish a job in 3 days. Diya alone takes 4 days. How many days would Ananya take alone?
- 3.Pooja works twice as fast as Rahul. Together they finish a job in 5 days. How many days would Rahul take alone?
- 4.Aarav can finish a job in 6 days and Ishaan in 12 days. Aarav works alone for 1 day and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 5.Vivaan can finish a job in 8 days and Priya in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 6.Priya can finish a job in 6 days and Nisha in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Rohan can finish a job in 20 days and Aarav in 8 days. What fraction of the job do they finish if they work together for 1 day? =
- 8.Saanvi can finish a job in 6 days and Kavya in 24 days. Saanvi works alone for 1 day and then stops. Kavya finishes the rest. How many days does Kavya take?
- 9.Dev can finish a job in 5 days and Aditya in 25 days. Dev works alone for 4 days and then stops. Aditya finishes the rest. How many days does Aditya take?
- 10.Vivaan can finish a job in 6 days and Aarav in 18 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 11.Kabir and Farhan together finish a job in 4 days. Kabir alone takes 6 days. How many days would Farhan take alone?
- 12.Aarav can finish a job in 2 days and Arjun in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 13.Manav and Isha together finish a job in 12 days. Manav alone takes 15 days. How many days would Isha take alone?
- 14.Rahul can finish a job in 7 days and Vivaan in 21 days. Rahul works alone for 4 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 15.Aditya and Dev together finish a job in 10 days. Aditya alone takes 12 days. How many days would Dev take alone?
- 16.Kabir works three times as fast as Aarav. Together they finish a job in 6 days. How many days would Aarav take alone?
- 17.Rohan can finish a job in 12 days and Tara in 24 days. Rohan works alone for 3 days and then stops. Tara finishes the rest. How many days does Tara take?
- 18.Rohan can finish a job in 10 days and Kavya in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 19.Karan works three times as fast as Rahul. Together they finish a job in 11 days. How many days would Rahul take alone?
- 20.Rahul and Ananya together finish a job in 2 days. Rahul alone takes 3 days. How many days would Ananya take alone?
- 21.Kavya can finish a job in 11 days and Zoya in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 22.Sneha works three times as fast as Tara. Together they finish a job in 12 days. How many days would Tara take alone?
- 23.Manav can finish a job in 6 days and Arjun in 4 days. Manav works alone for 3 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 24.Vivaan can finish a job in 18 days and Kavya in 30 days. Vivaan works alone for 3 days and then stops. Kavya finishes the rest. How many days does Kavya take?
- 25.Diya works twice as fast as Kabir. Together they finish a job in 5 days. How many days would Kabir take alone?
- 26.Pooja can finish a job in 11 days and Ananya in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 27.Zoya works three times as fast as Sneha. Together they finish a job in 9 days. How many days would Sneha take alone?
- 28.Ishaan can finish a job in 12 days and Aarav in 30 days. Ishaan works alone for 6 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 29.Ishaan can finish a job in 2 days and Saanvi in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 30.Meera can finish a job in 12 days and Karan in 27 days. Meera works alone for 4 days and then stops. Karan finishes the rest. How many days does Karan take?
- 31.Saanvi and Priya together finish a job in 5 days. Saanvi alone takes 6 days. How many days would Priya take alone?
- 32.Nisha can finish a job in 7 days and Kabir in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 33.Tara can finish a job in 11 days and Vivaan in 7 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 34.Kabir can finish a job in 12 days and Saanvi in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 35.Dev and Farhan together finish a job in 4 days. Dev alone takes 5 days. How many days would Farhan take alone?
- 36.Saanvi works three times as fast as Ananya. Together they finish a job in 5 days. How many days would Ananya take alone?
- 37.Zoya and Ananya together finish a job in 4 days. Zoya alone takes 6 days. How many days would Ananya take alone?
- 38.Rohan can finish a job in 13 days and Rahul in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 39.Ananya works twice as fast as Priya. Together they finish a job in 9 days. How many days would Priya take alone?
- 40.Aarav can finish a job in 7 days and Karan in 16 days. What fraction of the job do they finish if they work together for 3 days? =
Answer key
- 9
- 12
- 15
- 10
- 56/11
- 78/19
- 7/40
- 20
- 5
- 9/2
- 12
- 30/17
- 60
- 9
- 60
- 24
- 18
- 8/15
- 44
- 6
- 17/22
- 48
- 2
- 25
- 15
- 44/15
- 36
- 15
- 20/11
- 18
- 30
- 44/105
- 77/18
- 156/25
- 20
- 20
- 12
- 195/28
- 27
- 69/112