Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Meera works twice as fast as Pooja. Together they finish a job in 4 days. How many days would Pooja take alone?
- 2.Rahul can finish a job in 9 days and Aarav in 10 days. What fraction of the job do they finish if they work together for 1 day? =
- 3.Sneha can finish a job in 16 days and Rohan in 4 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 4.Saanvi can finish a job in 10 days and Kavya in 8 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Dev and Karan together finish a job in 6 days. Dev alone takes 8 days. How many days would Karan take alone?
- 6.Ananya can finish a job in 9 days and Kabir in 21 days. Ananya works alone for 3 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 7.Meera works three times as fast as Isha. Together they finish a job in 10 days. How many days would Isha take alone?
- 8.Ishaan can finish a job in 18 days and Aditya in 16 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 9.Farhan can finish a job in 2 days and Pooja in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 10.Ananya can finish a job in 4 days and Kabir in 28 days. Ananya works alone for 1 day and then stops. Kabir finishes the rest. How many days does Kabir take?
- 11.Dev can finish a job in 24 days and Diya in 6 days. Dev works alone for 16 days and then stops. Diya finishes the rest. How many days does Diya take?
- 12.Ananya works three times as fast as Vivaan. Together they finish a job in 4 days. How many days would Vivaan take alone?
- 13.Nisha works three times as fast as Sneha. Together they finish a job in 11 days. How many days would Sneha take alone?
- 14.Nisha can finish a job in 17 days and Meera in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 15.Aarav and Kavya together finish a job in 3 days. Aarav alone takes 6 days. How many days would Kavya take alone?
- 16.Kabir can finish a job in 19 days and Karan in 4 days. What fraction of the job do they finish if they work together for 1 day? =
- 17.Rahul works three times as fast as Kabir. Together they finish a job in 11 days. How many days would Kabir take alone?
- 18.Rahul and Pooja together finish a job in 2 days. Rahul alone takes 6 days. How many days would Pooja take alone?
- 19.Tara and Pooja together finish a job in 2 days. Tara alone takes 6 days. How many days would Pooja take alone?
- 20.Priya can finish a job in 4 days and Rohan in 15 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 21.Ananya and Aditya together finish a job in 2 days. Ananya alone takes 4 days. How many days would Aditya take alone?
- 22.Farhan can finish a job in 17 days and Aditya in 3 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Priya can finish a job in 18 days and Nisha in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 24.Zoya can finish a job in 21 days and Sneha in 9 days. Zoya works alone for 7 days and then stops. Sneha finishes the rest. How many days does Sneha take?
- 25.Kabir can finish a job in 9 days and Saanvi in 13 days. What fraction of the job do they finish if they work together for 2 days? =
- 26.Ananya can finish a job in 7 days and Dev in 28 days. Ananya works alone for 4 days and then stops. Dev finishes the rest. How many days does Dev take?
- 27.Farhan can finish a job in 9 days and Rohan in 18 days. Farhan works alone for 8 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 28.Kabir can finish a job in 20 days and Farhan in 4 days. Kabir works alone for 10 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 29.Ananya can finish a job in 11 days and Tara in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 30.Aditya can finish a job in 8 days and Rahul in 11 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Rahul can finish a job in 7 days and Tara in 28 days. Rahul works alone for 4 days and then stops. Tara finishes the rest. How many days does Tara take?
- 32.Rohan works three times as fast as Ananya. Together they finish a job in 10 days. How many days would Ananya take alone?
- 33.Dev can finish a job in 8 days and Ishaan in 13 days. What fraction of the job do they finish if they work together for 2 days? =
- 34.Rahul works twice as fast as Kavya. Together they finish a job in 2 days. How many days would Kavya take alone?
- 35.Ishaan works twice as fast as Diya. Together they finish a job in 7 days. How many days would Diya take alone?
- 36.Saanvi and Aarav together finish a job in 12 days. Saanvi alone takes 30 days. How many days would Aarav take alone?
- 37.Kavya works three times as fast as Diya. Together they finish a job in 4 days. How many days would Diya take alone?
- 38.Rohan can finish a job in 30 days and Meera in 27 days. Rohan works alone for 10 days and then stops. Meera finishes the rest. How many days does Meera take?
- 39.Manav can finish a job in 16 days and Karan in 28 days. Manav works alone for 8 days and then stops. Karan finishes the rest. How many days does Karan take?
- 40.Pooja works twice as fast as Rahul. Together they finish a job in 11 days. How many days would Rahul take alone?
Answer key
- 12
- 19/90
- 16/5
- 40/9
- 24
- 14
- 40
- 144/17
- 38/21
- 21
- 2
- 16
- 44
- 31/119
- 6
- 23/76
- 44
- 3
- 3
- 60/19
- 4
- 51/20
- 11/45
- 6
- 44/117
- 12
- 2
- 2
- 30/209
- 88/19
- 12
- 40
- 21/52
- 6
- 21
- 20
- 16
- 18
- 14
- 33
Free quantitative aptitude lessons, practice and worksheets at talentjr.in/quantitative-aptitude