Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Kavya can finish a job in 6 days and Farhan in 4 days. Kavya works alone for 3 days and then stops. Farhan finishes the rest. How many days does Farhan take?
- 2.Manav can finish a job in 6 days and Rohan in 21 days. Manav works alone for 4 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 3.Rohan can finish a job in 7 days and Meera in 14 days. What fraction of the job do they finish if they work together for 2 days? =
- 4.Ishaan can finish a job in 13 days and Kavya in 2 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 5.Sneha can finish a job in 18 days and Arjun in 14 days. Sneha works alone for 9 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 6.Kavya can finish a job in 9 days and Diya in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 7.Ananya and Manav together finish a job in 2 days. Ananya alone takes 4 days. How many days would Manav take alone?
- 8.Dev can finish a job in 10 days and Kabir in 18 days. What fraction of the job do they finish if they work together for 3 days? =
- 9.Pooja and Diya together finish a job in 4 days. Pooja alone takes 5 days. How many days would Diya take alone?
- 10.Kavya can finish a job in 20 days and Rohan in 12 days. Kavya works alone for 5 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 11.Aarav can finish a job in 4 days and Saanvi in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 12.Ishaan and Aarav together finish a job in 2 days. Ishaan alone takes 4 days. How many days would Aarav take alone?
- 13.Kavya and Isha together finish a job in 3 days. Kavya alone takes 4 days. How many days would Isha take alone?
- 14.Vivaan and Ishaan together finish a job in 3 days. Vivaan alone takes 4 days. How many days would Ishaan take alone?
- 15.Nisha can finish a job in 12 days and Manav in 26 days. Nisha works alone for 6 days and then stops. Manav finishes the rest. How many days does Manav take?
- 16.Dev can finish a job in 6 days and Aarav in 18 days. Dev works alone for 4 days and then stops. Aarav finishes the rest. How many days does Aarav take?
- 17.Dev works three times as fast as Ananya. Together they finish a job in 2 days. How many days would Ananya take alone?
- 18.Meera and Aarav together finish a job in 6 days. Meera alone takes 8 days. How many days would Aarav take alone?
- 19.Pooja can finish a job in 3 days and Sneha in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 20.Manav works twice as fast as Rahul. Together they finish a job in 5 days. How many days would Rahul take alone?
- 21.Kavya can finish a job in 7 days and Vivaan in 10 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 22.Diya works twice as fast as Aditya. Together they finish a job in 5 days. How many days would Aditya take alone?
- 23.Diya can finish a job in 16 days and Rohan in 15 days. What fraction of the job do they finish if they work together for 2 days? =
- 24.Tara can finish a job in 5 days and Sneha in 6 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 25.Dev can finish a job in 20 days and Nisha in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 26.Pooja works twice as fast as Priya. Together they finish a job in 4 days. How many days would Priya take alone?
- 27.Isha can finish a job in 5 days and Kabir in 20 days. Isha works alone for 2 days and then stops. Kabir finishes the rest. How many days does Kabir take?
- 28.Rohan works twice as fast as Sneha. Together they finish a job in 4 days. How many days would Sneha take alone?
- 29.Karan can finish a job in 11 days and Zoya in 16 days. What fraction of the job do they finish if they work together for 2 days? =
- 30.Sneha can finish a job in 11 days and Saanvi in 19 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 31.Farhan can finish a job in 4 days and Arjun in 14 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Aarav works three times as fast as Tara. Together they finish a job in 4 days. How many days would Tara take alone?
- 33.Ishaan can finish a job in 9 days and Zoya in 27 days. Ishaan works alone for 3 days and then stops. Zoya finishes the rest. How many days does Zoya take?
- 34.Rohan can finish a job in 7 days and Meera in 28 days. Rohan works alone for 6 days and then stops. Meera finishes the rest. How many days does Meera take?
- 35.Ishaan works three times as fast as Pooja. Together they finish a job in 11 days. How many days would Pooja take alone?
- 36.Diya works three times as fast as Rahul. Together they finish a job in 8 days. How many days would Rahul take alone?
- 37.Meera and Sneha together finish a job in 5 days. Meera alone takes 30 days. How many days would Sneha take alone?
- 38.Ananya works twice as fast as Saanvi. Together they finish a job in 10 days. How many days would Saanvi take alone?
- 39.Ishaan can finish a job in 28 days and Vivaan in 7 days. Ishaan works alone for 20 days and then stops. Vivaan finishes the rest. How many days does Vivaan take?
- 40.Diya works three times as fast as Vivaan. Together they finish a job in 4 days. How many days would Vivaan take alone?
Answer key
- 2
- 7
- 3/7
- 26/15
- 7
- 18/5
- 4
- 7/15
- 20
- 9
- 76/23
- 4
- 12
- 12
- 13
- 6
- 8
- 24
- 30/13
- 15
- 70/17
- 15
- 31/120
- 30/11
- 13/30
- 12
- 12
- 12
- 27/88
- 209/30
- 28/9
- 16
- 18
- 4
- 44
- 32
- 6
- 30
- 2
- 16