Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Your eco-club poster is due in 8 days. Research takes 2 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 2.✂️ Your team must make 24 bookmarks in 6 days, the same number each day. How many bookmarks a day?
- 3.🔍 Which is the odd one out? (a) no spare time (b) hard part first (c) using a simple timetable (d) listing tasks first
- 4.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) this week (c) after it is due (d) the night before
- 5.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 6.✂️ Your team must make 20 name badges in 5 days, the same number each day. How many name badges a day?
- 7.True or false: “forgetting the due date” is good project planning. (a) False (b) True
- 8.Which of these is good project planning? (a) one huge deadline (b) no spare time (c) starting on the last day (d) setting mini-deadlines
- 9.True or false: “using a simple timetable” is poor project planning. (a) True (b) False
- 10.🔍 Which is the odd one out? (a) setting mini-deadlines (b) guessing how long (c) using a simple timetable (d) keeping spare days
- 11.✅ What is a mini-deadline? (a) a late fine (b) the final due date (c) a date for one step (d) a holiday
- 12.True or false: “breaking work into steps” is good project planning. (a) False (b) True
- 13.Which of these is good project planning? (a) doing only easy bits (b) guessing how long (c) no task list (d) using a simple timetable
- 14.True or false: “listing tasks first” is poor project planning. (a) False (b) True
- 15.Which of these is poor project planning? (a) checking progress weekly (b) guessing how long (c) hard part first (d) listing tasks first
- 16.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 17.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) to start late (c) there is no need (d) for surprises
- 18.True or false: “no spare time” is good project planning. (a) False (b) True
- 19.📅 Your maths exhibit is due in 13 days. Research takes 3 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 20.🧩 A big project feels scary. What should you do first? (a) wait for help (b) break it into steps (c) give up (d) do it all at once
- 21.📅 Your history chart is due in 14 days. Research takes 4 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 22.Which of these is poor project planning? (a) starting on the last day (b) setting mini-deadlines (c) breaking work into steps (d) checking progress weekly
- 23.📅 Your eco-club poster is due in 9 days. Research takes 2 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 24.✂️ Your team must make 32 paper flowers in 4 days, the same number each day. How many paper flowers a day?
- 25.✂️ Your team must make 18 name badges in 2 days, the same number each day. How many name badges a day?
- 26.⏰ You start at 3:30 PM. Homework takes 40 minutes, then project work takes 15 minutes. When will you finish? (a) 3:45 PM (b) 4:10 PM (c) 4:40 PM (d) 4:25 PM
- 27.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 28.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) neither (c) study for the test (d) make the poster
- 29.True or false: “keeping spare days” is poor project planning. (a) False (b) True
- 30.📅 Your science model is due in 9 days. Research takes 2 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 31.📅 Your history chart is due in 10 days. Research takes 2 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 32.Which of these is poor project planning? (a) breaking work into steps (b) doing only easy bits (c) listing tasks first (d) using a simple timetable
- 33.🔍 Which is the odd one out? (a) no task list (b) no spare time (c) hard part first (d) starting on the last day
- 34.🔍 Which is the odd one out? (a) ignoring the timetable (b) breaking work into steps (c) listing tasks first (d) using a simple timetable
- 35.🔍 Which is the odd one out? (a) listing tasks first (b) ignoring the timetable (c) doing only easy bits (d) starting on the last day
- 36.🔍 Which is the odd one out? (a) checking progress weekly (b) ignoring the timetable (c) one huge deadline (d) guessing how long
- 37.🔍 Which is the odd one out? (a) no spare time (b) doing only easy bits (c) starting on the last day (d) setting mini-deadlines
- 38.⏰ You start at 4:30 PM. Homework takes 45 minutes, then project work takes 25 minutes. When will you finish? (a) 5:55 PM (b) 5:40 PM (c) 4:55 PM (d) 5:15 PM
- 39.True or false: “checking progress weekly” is good project planning. (a) False (b) True
- 40.Which of these is poor project planning? (a) forgetting the due date (b) breaking work into steps (c) hard part first (d) keeping spare days
Answer key
- 3
- 4
- no spare time
- this week
- good planning
- 4
- False
- setting mini-deadlines
- False
- guessing how long
- a date for one step
- True
- using a simple timetable
- False
- guessing how long
- poor planning
- for surprises
- False
- 2
- break it into steps
- 4
- starting on the last day
- 4
- 8
- 9
- 4:25 PM
- good planning
- study for the test
- False
- 2
- 5
- doing only easy bits
- hard part first
- ignoring the timetable
- listing tasks first
- checking progress weekly
- setting mini-deadlines
- 5:40 PM
- True
- forgetting the due date