Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) this week (c) in the third week (d) after it is due
- 2.Which of these is poor project planning? (a) setting mini-deadlines (b) guessing how long (c) checking progress weekly (d) starting early
- 3.Which of these is good project planning? (a) doing only easy bits (b) one huge deadline (c) forgetting the due date (d) breaking work into steps
- 4.True or false: “guessing how long” is good project planning. (a) True (b) False
- 5.🔍 Which is the odd one out? (a) listing tasks first (b) checking progress weekly (c) ignoring the timetable (d) hard part first
- 6.📅 Your science model is due in 10 days. Research takes 3 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 7.⏰ You start at 4:15 PM. Homework takes 40 minutes, then project work takes 35 minutes. When will you finish? (a) 4:55 PM (b) 5:45 PM (c) 5:30 PM (d) 4:50 PM
- 8.Which of these is good project planning? (a) starting on the last day (b) no task list (c) forgetting the due date (d) checking progress weekly
- 9.Which of these is poor project planning? (a) setting mini-deadlines (b) keeping spare days (c) doing only easy bits (d) checking progress weekly
- 10.True or false: “keeping spare days” is good project planning. (a) False (b) True
- 11.📅 Your eco-club poster is due in 7 days. Research takes 3 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 12.🔍 Which is the odd one out? (a) listing tasks first (b) breaking work into steps (c) one huge deadline (d) starting early
- 13.✂️ Your team must make 18 bookmarks in 2 days, the same number each day. How many bookmarks a day?
- 14.True or false: “checking progress weekly” is poor project planning. (a) False (b) True
- 15.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) play first (d) study for the test
- 16.🔍 Which is the odd one out? (a) doing only easy bits (b) starting on the last day (c) listing tasks first (d) forgetting the due date
- 17.True or false: “setting mini-deadlines” is good project planning. (a) False (b) True
- 18.📅 Your science model is due in 12 days. Research takes 4 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
- 19.✂️ Your team must make 20 paper bags in 5 days, the same number each day. How many paper bags a day?
- 20.Which of these is good project planning? (a) guessing how long (b) no task list (c) one huge deadline (d) using a simple timetable
- 21.True or false: “starting on the last day” is good project planning. (a) True (b) False
- 22.True or false: “starting early” is poor project planning. (a) True (b) False
- 23.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
- 24.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 25.True or false: “hard part first” is poor project planning. (a) True (b) False
- 26.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 27.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 28.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a date for one step (d) a holiday
- 29.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 30.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 31.True or false: “no spare time” is good project planning. (a) False (b) True
- 32.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
- 33.Which of these is good project planning? (a) forgetting the due date (b) doing only easy bits (c) no spare time (d) hard part first
- 34.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) wait for help (c) give up (d) do it all at once
- 35.True or false: “guessing how long” is poor project planning. (a) True (b) False
- 36.Which of these is poor project planning? (a) breaking work into steps (b) ignoring the timetable (c) setting mini-deadlines (d) keeping spare days
- 37.📅 Your class magazine is due in 10 days. Research takes 3 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 38.📅 Your eco-club poster is due in 12 days. Research takes 4 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 39.📅 Your eco-club poster is due in 16 days. Research takes 4 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 40.⏰ You start at 5:45 PM. Homework takes 25 minutes, then project work takes 15 minutes. When will you finish? (a) 6:10 PM (b) 6:25 PM (c) 6:40 PM (d) 6:00 PM
Answer key
- this week
- guessing how long
- breaking work into steps
- False
- ignoring the timetable
- 1
- 5:30 PM
- checking progress weekly
- doing only easy bits
- True
- 1
- one huge deadline
- 9
- False
- study for the test
- listing tasks first
- True
- 1
- 4
- using a simple timetable
- False
- False
- good planning
- poor planning
- False
- poor planning
- poor planning
- a date for one step
- poor planning
- good planning
- False
- poor planning
- hard part first
- break it into steps
- True
- ignoring the timetable
- 1
- 3
- 5
- 6:25 PM