Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) the night before (d) after it is due
- 2.🔍 Which is the odd one out? (a) using a simple timetable (b) listing tasks first (c) no spare time (d) starting early
- 3.True or false: “listing tasks first” is poor project planning. (a) False (b) True
- 4.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
- 5.Which of these is good project planning? (a) guessing how long (b) one huge deadline (c) forgetting the due date (d) starting early
- 6.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
- 7.✂️ Your team must make 12 thank-you cards in 3 days, the same number each day. How many thank-you cards a day?
- 8.✅ What is a mini-deadline? (a) the final due date (b) a holiday (c) a date for one step (d) a late fine
- 9.Which of these is good project planning? (a) ignoring the timetable (b) no spare time (c) using a simple timetable (d) one huge deadline
- 10.Which of these is poor project planning? (a) setting mini-deadlines (b) ignoring the timetable (c) starting early (d) keeping spare days
- 11.True or false: “forgetting the due date” is good project planning. (a) True (b) False
- 12.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 13.True or false: “no task list” is good project planning. (a) True (b) False
- 14.✂️ Your team must make 24 posters in 4 days, the same number each day. How many posters a day?
- 15.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) make the poster (b) play first (c) study for the test (d) neither
- 16.📅 Your eco-club poster is due in 10 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 17.Which of these is good project planning? (a) doing only easy bits (b) starting on the last day (c) no task list (d) breaking work into steps
- 18.🔍 Which is the odd one out? (a) ignoring the timetable (b) starting early (c) listing tasks first (d) setting mini-deadlines
- 19.🔍 Which is the odd one out? (a) hard part first (b) no task list (c) checking progress weekly (d) using a simple timetable
- 20.🔍 Which is the odd one out? (a) guessing how long (b) using a simple timetable (c) checking progress weekly (d) starting early
- 21.True or false: “checking progress weekly” is good project planning. (a) True (b) False
- 22.Which of these is poor project planning? (a) one huge deadline (b) keeping spare days (c) setting mini-deadlines (d) checking progress weekly
- 23.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) for surprises (c) there is no need (d) to start late
- 24.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) give up (c) do it all at once (d) wait for help
- 25.True or false: “no spare time” is good project planning. (a) True (b) False
- 26.⏰ You start at 3:00 PM. Homework takes 30 minutes, then project work takes 25 minutes. When will you finish? (a) 3:25 PM (b) 3:30 PM (c) 4:10 PM (d) 3:55 PM
- 27.True or false: “breaking work into steps” is poor project planning. (a) True (b) False
- 28.True or false: “breaking work into steps” is good project planning. (a) False (b) True
- 29.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
- 30.Which of these is good project planning? (a) no task list (b) one huge deadline (c) starting on the last day (d) keeping spare days
- 31.Which of these is poor project planning? (a) listing tasks first (b) guessing how long (c) keeping spare days (d) checking progress weekly
- 32.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 33.True or false: “ignoring the timetable” is poor project planning. (a) True (b) False
- 34.Which of these is poor project planning? (a) keeping spare days (b) setting mini-deadlines (c) hard part first (d) forgetting the due date
- 35.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 36.🔍 Which is the odd one out? (a) starting early (b) using a simple timetable (c) setting mini-deadlines (d) one huge deadline
- 37.Which of these is poor project planning? (a) hard part first (b) doing only easy bits (c) breaking work into steps (d) keeping spare days
- 38.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 39.📅 Your history chart is due in 13 days. Research takes 3 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 40.Which of these is good project planning? (a) forgetting the due date (b) doing only easy bits (c) no spare time (d) checking progress weekly
Answer key
- this week
- no spare time
- False
- True
- starting early
- False
- 4
- a date for one step
- using a simple timetable
- ignoring the timetable
- False
- good planning
- False
- 6
- study for the test
- 5
- breaking work into steps
- ignoring the timetable
- no task list
- guessing how long
- True
- one huge deadline
- for surprises
- break it into steps
- False
- 3:55 PM
- False
- True
- poor planning
- keeping spare days
- guessing how long
- good planning
- True
- forgetting the due date
- False
- one huge deadline
- doing only easy bits
- poor planning
- 5
- checking progress weekly