Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.Which of these is poor project planning? (a) starting early (b) checking progress weekly (c) one huge deadline (d) hard part first
- 2.Which of these is poor project planning? (a) listing tasks first (b) using a simple timetable (c) breaking work into steps (d) ignoring the timetable
- 3.⏰ You start at 5:45 PM. Homework takes 30 minutes, then project work takes 40 minutes. When will you finish? (a) 6:55 PM (b) 7:10 PM (c) 6:25 PM (d) 6:15 PM
- 4.True or false: “ignoring the timetable” is poor project planning. (a) True (b) False
- 5.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 6.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 7.True or false: “starting early” is good project planning. (a) True (b) False
- 8.✂️ Your team must make 18 thank-you cards in 2 days, the same number each day. How many thank-you cards a day?
- 9.🔍 Which is the odd one out? (a) one huge deadline (b) forgetting the due date (c) setting mini-deadlines (d) no task list
- 10.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) this week (c) in the third week (d) after it is due
- 11.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
- 12.📅 Your class magazine is due in 13 days. Research takes 2 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 13.Which of these is poor project planning? (a) no spare time (b) keeping spare days (c) using a simple timetable (d) hard part first
- 14.🧩 A big project feels scary. What should you do first? (a) give up (b) do it all at once (c) break it into steps (d) wait for help
- 15.🔍 Which is the odd one out? (a) doing only easy bits (b) keeping spare days (c) checking progress weekly (d) setting mini-deadlines
- 16.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 17.🔍 Which is the odd one out? (a) checking progress weekly (b) breaking work into steps (c) forgetting the due date (d) hard part first
- 18.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) play first (c) neither (d) make the poster
- 19.✂️ Your team must make 30 paper flowers in 6 days, the same number each day. How many paper flowers a day?
- 20.Which of these is good project planning? (a) doing only easy bits (b) listing tasks first (c) forgetting the due date (d) no spare time
- 21.Which of these is good project planning? (a) hard part first (b) guessing how long (c) doing only easy bits (d) no spare time
- 22.Which of these is good project planning? (a) forgetting the due date (b) breaking work into steps (c) doing only easy bits (d) ignoring the timetable
- 23.Which of these is good project planning? (a) ignoring the timetable (b) guessing how long (c) no spare time (d) keeping spare days
- 24.🔍 Which is the odd one out? (a) starting on the last day (b) hard part first (c) doing only easy bits (d) one huge deadline
- 25.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 26.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
- 27.True or false: “one huge deadline” is poor project planning. (a) True (b) False
- 28.Which of these is good project planning? (a) no spare time (b) guessing how long (c) starting on the last day (d) setting mini-deadlines
- 29.Which of these is good project planning? (a) no spare time (b) starting on the last day (c) using a simple timetable (d) no task list
- 30.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 31.🔍 Which is the odd one out? (a) one huge deadline (b) no task list (c) no spare time (d) using a simple timetable
- 32.Which of these is poor project planning? (a) using a simple timetable (b) listing tasks first (c) guessing how long (d) starting early
- 33.📅 Your art display is due in 13 days. Research takes 2 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 34.True or false: “no task list” is good project planning. (a) False (b) True
- 35.True or false: “keeping spare days” is poor project planning. (a) False (b) True
- 36.✂️ Your team must make 6 name badges in 2 days, the same number each day. How many name badges a day?
- 37.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
- 38.🔍 Which is the odd one out? (a) starting early (b) starting on the last day (c) forgetting the due date (d) no task list
- 39.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 40.True or false: “no spare time” is good project planning. (a) True (b) False
Answer key
- one huge deadline
- ignoring the timetable
- 6:55 PM
- True
- poor planning
- good planning
- True
- 9
- setting mini-deadlines
- this week
- True
- 4
- no spare time
- break it into steps
- doing only easy bits
- good planning
- forgetting the due date
- study for the test
- 5
- listing tasks first
- hard part first
- breaking work into steps
- keeping spare days
- hard part first
- poor planning
- good planning
- True
- setting mini-deadlines
- using a simple timetable
- poor planning
- using a simple timetable
- guessing how long
- 4
- False
- False
- 3
- False
- starting early
- good planning
- False