Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 803 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) the night before (c) after it is due (d) this week
  2. 2.✂️ Your team must make 12 posters in 2 days, the same number each day. How many posters a day?
  3. 3.True or false: “breaking work into steps” is good project planning. (a) False (b) True
  4. 4.⏳ Why keep a spare day or two before the deadline? (a) for surprises (b) to start late (c) to rest only (d) there is no need
  5. 5.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
  6. 6.Which of these is poor project planning? (a) hard part first (b) using a simple timetable (c) keeping spare days (d) no spare time
  7. 7.✂️ Your team must make 40 paper bags in 5 days, the same number each day. How many paper bags a day?
  8. 8.⏰ You start at 3:15 PM. Homework takes 35 minutes, then project work takes 25 minutes. When will you finish? (a) 3:40 PM (b) 4:15 PM (c) 4:30 PM (d) 3:50 PM
  9. 9.⏰ You start at 5:15 PM. Homework takes 20 minutes, then project work takes 40 minutes. When will you finish? (a) 5:55 PM (b) 6:30 PM (c) 5:35 PM (d) 6:15 PM
  10. 10.📅 Your art display is due in 10 days. Research takes 4 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  11. 11.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
  12. 12.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
  13. 13.📅 Your eco-club poster is due in 14 days. Research takes 3 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
  14. 14.True or false: “starting early” is poor project planning. (a) True (b) False
  15. 15.📅 Your history chart is due in 10 days. Research takes 2 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  16. 16.Which of these is poor project planning? (a) hard part first (b) breaking work into steps (c) one huge deadline (d) checking progress weekly
  17. 17.📅 Your class magazine is due in 10 days. Research takes 2 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
  18. 18.Which of these is poor project planning? (a) starting early (b) setting mini-deadlines (c) hard part first (d) starting on the last day
  19. 19.True or false: “starting on the last day” is good project planning. (a) True (b) False
  20. 20.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
  21. 21.✂️ Your team must make 21 thank-you cards in 3 days, the same number each day. How many thank-you cards a day?
  22. 22.⏰ You start at 5:30 PM. Homework takes 20 minutes, then project work takes 15 minutes. When will you finish? (a) 6:20 PM (b) 5:45 PM (c) 6:05 PM (d) 5:50 PM
  23. 23.Which of these is good project planning? (a) ignoring the timetable (b) using a simple timetable (c) starting on the last day (d) guessing how long
  24. 24.⏰ You start at 5:00 PM. Homework takes 40 minutes, then project work takes 25 minutes. When will you finish? (a) 6:05 PM (b) 5:40 PM (c) 5:25 PM (d) 6:20 PM
  25. 25.🔍 Which is the odd one out? (a) breaking work into steps (b) ignoring the timetable (c) forgetting the due date (d) starting on the last day
  26. 26.⏰ You start at 3:30 PM. Homework takes 40 minutes, then project work takes 20 minutes. When will you finish? (a) 4:45 PM (b) 4:30 PM (c) 4:10 PM (d) 3:50 PM
  27. 27.🔍 Which is the odd one out? (a) hard part first (b) no spare time (c) starting early (d) listing tasks first
  28. 28.Which of these is good project planning? (a) no spare time (b) no task list (c) forgetting the due date (d) setting mini-deadlines
  29. 29.🔍 Which is the odd one out? (a) setting mini-deadlines (b) ignoring the timetable (c) using a simple timetable (d) hard part first
  30. 30.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
  31. 31.📅 Your class magazine is due in 10 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  32. 32.🔍 Which is the odd one out? (a) setting mini-deadlines (b) starting early (c) starting on the last day (d) checking progress weekly
  33. 33.Which of these is good project planning? (a) doing only easy bits (b) guessing how long (c) starting on the last day (d) hard part first
  34. 34.✅ What is a mini-deadline? (a) a holiday (b) a late fine (c) the final due date (d) a date for one step
  35. 35.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
  36. 36.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) make the poster (b) neither (c) play first (d) study for the test
  37. 37.🔍 Which is the odd one out? (a) starting early (b) checking progress weekly (c) hard part first (d) no task list
  38. 38.True or false: “keeping spare days” is poor project planning. (a) False (b) True
  39. 39.🔍 Which is the odd one out? (a) listing tasks first (b) keeping spare days (c) setting mini-deadlines (d) doing only easy bits
  40. 40.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning

Answer key

  1. this week
  2. 6
  3. True
  4. for surprises
  5. good planning
  6. no spare time
  7. 8
  8. 4:15 PM
  9. 6:15 PM
  10. 1
  11. poor planning
  12. poor planning
  13. 5
  14. False
  15. 4
  16. one huge deadline
  17. 2
  18. starting on the last day
  19. False
  20. poor planning
  21. 7
  22. 6:05 PM
  23. using a simple timetable
  24. 6:05 PM
  25. breaking work into steps
  26. 4:30 PM
  27. no spare time
  28. setting mini-deadlines
  29. ignoring the timetable
  30. good planning
  31. 5
  32. starting on the last day
  33. hard part first
  34. a date for one step
  35. good planning
  36. study for the test
  37. no task list
  38. False
  39. doing only easy bits
  40. poor planning