Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 990 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) this week (c) in the third week (d) after it is due
  2. 2.✂️ Your team must make 12 posters in 2 days, the same number each day. How many posters a day?
  3. 3.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
  4. 4.✂️ Your team must make 28 paper flowers in 4 days, the same number each day. How many paper flowers a day?
  5. 5.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
  6. 6.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  7. 7.🔍 Which is the odd one out? (a) no spare time (b) starting early (c) one huge deadline (d) starting on the last day
  8. 8.✅ What is a mini-deadline? (a) the final due date (b) a holiday (c) a date for one step (d) a late fine
  9. 9.Which of these is poor project planning? (a) breaking work into steps (b) hard part first (c) setting mini-deadlines (d) guessing how long
  10. 10.Which of these is good project planning? (a) ignoring the timetable (b) starting on the last day (c) one huge deadline (d) listing tasks first
  11. 11.🔍 Which is the odd one out? (a) setting mini-deadlines (b) breaking work into steps (c) doing only easy bits (d) checking progress weekly
  12. 12.🔍 Which is the odd one out? (a) keeping spare days (b) hard part first (c) guessing how long (d) breaking work into steps
  13. 13.🔍 Which is the odd one out? (a) ignoring the timetable (b) listing tasks first (c) hard part first (d) keeping spare days
  14. 14.🔍 Which is the odd one out? (a) guessing how long (b) starting on the last day (c) hard part first (d) ignoring the timetable
  15. 15.🔍 Which is the odd one out? (a) keeping spare days (b) using a simple timetable (c) hard part first (d) starting on the last day
  16. 16.⏰ You start at 3:30 PM. Homework takes 40 minutes, then project work takes 15 minutes. When will you finish? (a) 3:45 PM (b) 4:10 PM (c) 4:40 PM (d) 4:25 PM
  17. 17.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
  18. 18.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
  19. 19.Which of these is good project planning? (a) guessing how long (b) ignoring the timetable (c) hard part first (d) starting on the last day
  20. 20.Which of these is poor project planning? (a) listing tasks first (b) forgetting the due date (c) breaking work into steps (d) setting mini-deadlines
  21. 21.True or false: “starting on the last day” is good project planning. (a) False (b) True
  22. 22.Which of these is good project planning? (a) no spare time (b) using a simple timetable (c) guessing how long (d) starting on the last day
  23. 23.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) do it all at once (d) break it into steps
  24. 24.✂️ Your team must make 15 bookmarks in 5 days, the same number each day. How many bookmarks a day?
  25. 25.🔍 Which is the odd one out? (a) one huge deadline (b) no task list (c) setting mini-deadlines (d) starting on the last day
  26. 26.Which of these is good project planning? (a) starting on the last day (b) guessing how long (c) starting early (d) doing only easy bits
  27. 27.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
  28. 28.Which of these is poor project planning? (a) setting mini-deadlines (b) keeping spare days (c) ignoring the timetable (d) listing tasks first
  29. 29.True or false: “starting on the last day” is poor project planning. (a) True (b) False
  30. 30.Which of these is poor project planning? (a) starting early (b) using a simple timetable (c) checking progress weekly (d) starting on the last day
  31. 31.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) to start late (c) for surprises (d) there is no need
  32. 32.📅 Your art display is due in 11 days. Research takes 4 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
  33. 33.🔍 Which is the odd one out? (a) no task list (b) checking progress weekly (c) starting early (d) keeping spare days
  34. 34.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
  35. 35.📅 Your science model is due in 10 days. Research takes 1 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
  36. 36.True or false: “forgetting the due date” is poor project planning. (a) False (b) True
  37. 37.True or false: “guessing how long” is good project planning. (a) False (b) True
  38. 38.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  39. 39.📅 Your eco-club poster is due in 8 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  40. 40.⏰ You start at 5:30 PM. Homework takes 40 minutes, then project work takes 20 minutes. When will you finish? (a) 6:10 PM (b) 6:30 PM (c) 6:45 PM (d) 5:50 PM

Answer key

  1. this week
  2. 6
  3. False
  4. 7
  5. poor planning
  6. good planning
  7. starting early
  8. a date for one step
  9. guessing how long
  10. listing tasks first
  11. doing only easy bits
  12. guessing how long
  13. ignoring the timetable
  14. hard part first
  15. starting on the last day
  16. 4:25 PM
  17. poor planning
  18. good planning
  19. hard part first
  20. forgetting the due date
  21. False
  22. using a simple timetable
  23. break it into steps
  24. 3
  25. setting mini-deadlines
  26. starting early
  27. poor planning
  28. ignoring the timetable
  29. True
  30. starting on the last day
  31. for surprises
  32. 3
  33. no task list
  34. good planning
  35. 4
  36. True
  37. False
  38. good planning
  39. 1
  40. 6:30 PM