Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.Which of these is good project planning? (a) setting mini-deadlines (b) ignoring the timetable (c) no task list (d) starting on the last day
- 2.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
- 3.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 4.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 5.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 6.Which of these is good project planning? (a) one huge deadline (b) ignoring the timetable (c) listing tasks first (d) starting on the last day
- 7.📅 Your maths exhibit is due in 11 days. Research takes 1 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
- 8.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) wait for help (c) give up (d) do it all at once
- 9.True or false: “keeping spare days” is good project planning. (a) False (b) True
- 10.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) this week (c) the night before (d) in the third week
- 11.⏳ Why keep a spare day or two before the deadline? (a) for surprises (b) to start late (c) to rest only (d) there is no need
- 12.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 13.Which of these is good project planning? (a) forgetting the due date (b) guessing how long (c) using a simple timetable (d) ignoring the timetable
- 14.🔍 Which is the odd one out? (a) one huge deadline (b) starting on the last day (c) doing only easy bits (d) keeping spare days
- 15.🔍 Which is the odd one out? (a) one huge deadline (b) breaking work into steps (c) starting on the last day (d) ignoring the timetable
- 16.Which of these is poor project planning? (a) no task list (b) using a simple timetable (c) listing tasks first (d) starting early
- 17.✂️ Your team must make 10 paper flowers in 2 days, the same number each day. How many paper flowers a day?
- 18.True or false: “setting mini-deadlines” is good project planning. (a) True (b) False
- 19.✅ What is a mini-deadline? (a) a holiday (b) the final due date (c) a date for one step (d) a late fine
- 20.Which of these is poor project planning? (a) one huge deadline (b) starting early (c) checking progress weekly (d) listing tasks first
- 21.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
- 22.🔍 Which is the odd one out? (a) keeping spare days (b) forgetting the due date (c) breaking work into steps (d) listing tasks first
- 23.📅 Your maths exhibit is due in 13 days. Research takes 3 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 24.✂️ Your team must make 30 name badges in 6 days, the same number each day. How many name badges a day?
- 25.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 26.Which of these is poor project planning? (a) using a simple timetable (b) checking progress weekly (c) hard part first (d) doing only easy bits
- 27.🔍 Which is the odd one out? (a) one huge deadline (b) hard part first (c) no task list (d) no spare time
- 28.✂️ Your team must make 6 paper flowers in 2 days, the same number each day. How many paper flowers a day?
- 29.🔍 Which is the odd one out? (a) no spare time (b) guessing how long (c) doing only easy bits (d) using a simple timetable
- 30.True or false: “starting on the last day” is good project planning. (a) True (b) False
- 31.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 32.True or false: “forgetting the due date” is good project planning. (a) True (b) False
- 33.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
- 34.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
- 35.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 36.True or false: “one huge deadline” is good project planning. (a) True (b) False
- 37.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
- 38.Which of these is poor project planning? (a) ignoring the timetable (b) checking progress weekly (c) listing tasks first (d) hard part first
- 39.📅 Your maths exhibit is due in 10 days. Research takes 4 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 40.🔍 Which is the odd one out? (a) keeping spare days (b) one huge deadline (c) hard part first (d) starting early
Answer key
- setting mini-deadlines
- good planning
- good planning
- poor planning
- good planning
- listing tasks first
- 3
- break it into steps
- True
- this week
- for surprises
- good planning
- using a simple timetable
- keeping spare days
- breaking work into steps
- no task list
- 5
- True
- a date for one step
- one huge deadline
- True
- forgetting the due date
- 4
- 5
- good planning
- doing only easy bits
- hard part first
- 3
- using a simple timetable
- False
- good planning
- False
- poor planning
- poor planning
- poor planning
- False
- poor planning
- ignoring the timetable
- 1
- one huge deadline